File #: 14-0681    Version: 1
Type: Agenda Item Status: Deferred
File created: 6/27/2014 In control: Procurement Committee
On agenda: 7/10/2014 Final action: 7/10/2014
Title: Authority to award Contract 14-942-11, Job Order Contracting Services, to Meccor Industries Ltd., in an amount not to exceed $8,000,000.00, Accounts 101, 201, 401-VAR-VAR
Attachments: 1. 08-AA.pdf
TRANSMITTAL LETTER FOR BOARD MEETING OF JULY 10, 2014
 
COMMITTEE ON PROCUREMENT
 
Mr. David St. Pierre, Executive Director
 
Title
Authority to award Contract 14-942-11, Job Order Contracting Services, to Meccor Industries Ltd., in an amount not to exceed $8,000,000.00, Accounts 101, 201, 401-VAR-VAR
Body
 
Dear Sir:
 
On February 20, 2014, the Board of Commissioners authorized the Director of Procurement and Materials Management to advertise for bids for Contract 14-942-11 Job Order Contracting Services, in an amount not to exceed $8,000,000.00.  The term of the contract will be for 24 months and will include an option for two additional one-year periods in the amount of $4,000,000.00 per year with Board approval.
 
In response to a public advertisement of April 9, 2014, a bid opening was held on May 6, 2014.  The bid tabulation for this contract is:
                            COMBINED ADJUSTMENT FACTOR                  
MECCOR INDUSTRIES LTD.      0.7700
F. H. PASCHEN, SN NIELSEN & ASSOCIATES, LLC      0.8761
DIVANE BROS. ELECTRIC COMPANY      0.9859
OLD VETERAN CONSTRUCTION, INC.      1.0000
MILLER, K.R. CONTRACTORS INC.      1.0428
 
Five hundred fifty-two (552) companies were notified of the contract being advertised and twenty-nine (29) companies requested specifications.
 
The basis for award of contract is determined by the firm who submitted the lowest combined adjustment factor.
 
Meccor Industries Ltd., the lowest responsible bidder, is proposing to perform this contract in accordance with the specifications and contract documents.
 
Meccor Industries Ltd., has executed the Multi-Project Labor Agreement certificate as required.  It is anticipated that various types of trades may be utilized on this contract based on the scope of work to be completed.  The utilization of any construction trades is not intended to confer any rights or jurisdiction upon any union or unions.
 
Meccor Industries Ltd., agrees to comply with the percentage requirements for utilization, established at 20 percent for Minority Business Enterprise (MBE), 10 percent for Women Business Enterprise (WBE), and 10 percent for Small Business Enterprise (SBE) goals.
 
In view of the foregoing, it is recommended that the Director of Procurement and Materials Management be authorized to award Contract 14-942-11 to Meccor Industries Ltd., in an amount not to exceed $8,000,000.00, subject to the contractor furnishing a performance and payment bond in form satisfactory to the Law Department and approved by the Director of Procurement and Materials Management.
 
Funds for the 2014 expenditure in the amount of $4,000,000.00 are available in Accounts 101, 201, 401-VAR-VAR.  The estimated expenditure for 2015 is $3,000,000.00 and for 2016 is $1,000,000.00.  Funds for the 2015 and 2016 expenditures are contingent on the Board of Commissioners' approval of the District's budget for that year.
 
Recommended, Darlene A. LoCascio, Director of Procurement and Materials Management, DAL:SEB:cm
Respectfully Submitted, Barbara J. McGowan, Chairman, Committee on Procurement
Disposition of this agenda item will be documented in the official Regular Board Meeting Minutes of the Board of Commissioners for July 10, 2014
 