To watch the live meeting proceedings, please refresh this page at the scheduled meeting time, a link labeled "In Progress" will appear under the Video column
File #: 14-1202    Version: 1
Type: Report Status: Filed
File created: 10/6/2014 In control: Stormwater Management Committee
On agenda: 10/16/2014 Final action: 10/16/2014
Title: Report on the District’s funding contribution for the Deer Creek Reservoir
TRANSMITTAL LETTER FOR BOARD MEETING OF OCTOBER 16, 2014
 
COMMITTEE ON STORMWATER MANAGEMENT
 
Mr. David St. Pierre, Executive Director
 
Title
Report on the District's funding contribution for the Deer Creek Reservoir
Body
 
Dear Sir:
 
On March 3, 2011, the Board of Commissioners approved funding, in the amount of $659,337.00, to be provided to the U.S. Army Corps of Engineers (Corps), on behalf of the Village of Ford Heights (Village), to allow for completion of the Deer Creek Reservoir, a flood control project that provides benefits to residents of the Village.  On March 17, 2011, the Board of Commissioners authorized disbursement of this contribution to the Corps. It was stated at that time that upon completion of the project the Corps would return any unused funds to the District.
 
Earlier this year, the Corps completed the remaining work on the Deer Creek Reservoir.  The Corps recently completed the final accounting and determined that $54,528.46 was to be returned to the District. On September 25, 2014, the District received these funds from the Corps and placed them into Account 501-50000-460690, Stormwater Management Fund.
 
Respectfully Submitted, Catherine A. O'Connor, Director of Engineering, WSS:JPM