Report on change orders authorized and approved by the Director of Engineering during the month of September 2014
Body
Dear Sir:
Four change orders were approved by the Director of Engineering that cumulatively, but not individually, increased or decreased the value of the purchase order by $10,000.00 or less during September 2014. The contracts and related data are listed in the attached sheet.
Two change orders were approved by the Director of Engineering on contracts with a 5% contingency provision for errors and omissions and unforeseen circumstances, for an increase or decrease of $100,000.00 or less during September 2014.
Please advise the undersigned if additional information is required.
Respectfully Submitted, Catherine A. O'Connor, Director of Engineering, MVL