TRANSMITTAL LETTER FOR BOARD MEETING OF NOVEMBER 20, 2014
COMMITTEE ON ENGINEERING
Mr. David St. Pierre, Executive Director
Title
Report on change orders authorized and approved by the Director of Engineering during the month of October 2014
Body
Dear Sir:
Eight change orders were approved by the Director of Engineering that cumulatively, but not individually, increased or decreased the value of the purchase order by $10,000.00 or less during October 2014.
Two change orders were approved by the Director of Engineering on contracts with a 5% contingency provision for errors and omissions and unforeseen circumstances, for an increase or decrease of $100,000.00 or less during October 2014.
The contracts and related data are listed in the attached sheets.
Please advise the undersigned if additional information is required.
Respectfully Submitted, Catherine A. O'Connor, Director of Engineering, MVL
Attachments