TRANSMITTAL LETTER FOR BOARD MEETING OF MARCH 19, 2015
COMMITTEE ON ENGINEERING
Mr. David St. Pierre, Executive Director
Title
Report on change orders authorized and approved by the Director of Engineering during the month of February 2015
Body
Dear Sir:
No change orders were approved by the Director of Engineering that cumulatively, but not individually, increased or decreased the value of the purchase order by $10,000.00 or less during February 2015.
Six change orders were approved by the Director of Engineering on contracts with a 5% contingency provision for errors and omissions and unforeseen circumstances, for an increase or decrease of $100,000.00 or less during February 2015. The contracts and related data are listed in Attachment 1.
Please advise the undersigned if additional information is required.
Respectfully Submitted, Catherine A. O'Connor, Director of Engineering, MVL
Attachment