TRANSMITTAL LETTER FOR BOARD MEETING OF APRIL 9, 2015
COMMITTEE ON PROCUREMENT
Mr. David St. Pierre, Executive Director
Title
Report of bid opening of Tuesday, March 31, 2015
Body
Dear Sir:
Bids were received and opened on 3/31/2015 for the following contracts:
CONTRACT 13-409-3P NITROGEN REMOVAL IN CENTRATE, EGAN WRP
LOCATION: EGAN
ESTIMATE: $3,200,000.00
GROUP: TOTAL
IHC CONSTRUCTION COMPANY.LLC $2,675,000.00
PATH CONSTRUCTION COMPANY, INC. $2,786,300.00
JOSEPH J. HENDERSON & SON, INC. $2,947,000.00
INDEPENDENT MECHANICAL INDUSTRIES, INC. $3,055,250.00
BIDDERS NOTIFIED: 602 PLANHOLDERS: 30
CONTRACT 15-801-21 REPLACE A CRANE MAINTENANCE PLATFORM AT THE CALUMET WATER RECLAMATION PLANT
LOCATION: CALUMET
ESTIMATE: $50,000.00
GROUP: TOTAL
SIEVERT ELECTRIC SERVICE AND SALES COMPANY $49,150.00
BIDDERS NOTIFIED: 418 PLANHOLDERS: 9
Respectfully Submitted, Darlene A. LoCascio, Director of Procurement and Materials Management