TRANSMITTAL LETTER FOR BOARD MEETING OF MAY 21, 2015
COMMITTEE ON ENGINEERING
Mr. David St. Pierre, Executive Director
Title
Report on change orders authorized and approved by the Director of Engineering during the month of April 2015
Body
Dear Sir:
Four change orders were approved by the Director of Engineering that cumulatively, but not individually, increased or decreased the value of the purchase order by $10,000.00 or less during April 2015. The contracts and related data are listed in Attachment 1.
Four change orders were approved by the Director of Engineering on contracts with a 5% contingency provision for errors and omissions and unforeseen circumstances, for an increase or decrease of $100,000.00 or less during April 2015. The contracts and related data are listed in Attachment 2.
Please advise the undersigned if additional information is required.
Respectfully Submitted, Catherine A. O'Connor, Director of Engineering, MVL
Attachments