File #: 15-0620    Version: 1
Type: Agenda Item Status: Adopted
File created: 6/5/2015 In control: Procurement Committee
On agenda: 6/18/2015 Final action: 6/18/2015
Title: Authority to increase Contract 04-203-4F Final Reservoir Preparation, Thornton Composite Reservoir, Calumet Service Area, to Walsh/II in One, Joint Venture in an amount of $92,477.40, from an amount of $50,941,242.55, to an amount not to exceed $51,033,719.95, Account 401-50000-645600, Purchase Order 5001224
Attachments: 1. CO Log 04-203-4F.pdf
TRANSMITTAL LETTER FOR BOARD MEETING OF JUNE 18, 2015
 
COMMITTEE ON Procurement
 
Mr. David St. Pierre, Executive Director      
 
Title
Authority to increase Contract 04-203-4F Final Reservoir Preparation, Thornton Composite Reservoir, Calumet Service Area, to Walsh/II in One, Joint Venture in an amount of $92,477.40, from an amount of $50,941,242.55, to an amount not to exceed $51,033,719.95, Account 401-50000-645600, Purchase Order 5001224
Body
 
Dear Sir:
 
On December 2, 2010, the Board of Commissioners authorized the Director of Procurement and Materials Management to award Contract 04-203-4F Final Reservoir Preparation, Thornton Composite Reservoir, Calumet Service Area, to Walsh/II in One, Joint Venture, in an amount not to exceed $50,763,937.00.  The scheduled contract completion date is November 1, 2015.
 
As of June 5, 2015, the attached list of change orders has been approved.  The effect of these change orders resulted in an increase in an amount of $177,305.55 from the original amount awarded of $50,763,937.00.  The current contract value is $50,941,242.55.  The prior approved change orders reflect a 0.35% increase to the original contract value.
 
The 04-201-4F Tollway Dam, Grout Curtain and Quarry Plugs contract specified overburden earthen material to be moved temporarily to the west side of the North Lobe to allow for the construction of the grout curtain.  The subject contract, 04-203-4F Final Reservoir Preparation, includes final grading of the overburden material on the north side of the reservoir.  The contractor advised the District that the quantity of earthwork on the site exceeds that specified in the contract documents.  This change order is to redistribute the additional earthen material to achieve a balanced final landscape.  The contractor submitted a cost proposal (CCO-019) for an extra in the amount of $92,477.40.  The engineer reviewed the proposal, found it to be reasonable, and stated via correspondence 625 that the Engineering Department would recommend its approval.
 
This change order is in compliance with the Illinois Criminal Code since the change is germane to the contract.
 
It is hereby recommended that the Board of Commissioners authorize the Director of Procurement and Materials Management to execute a change order to increase Contract 04-203-4F in an amount of $92,477.40 (0.18% of the current contract value), from an amount of $50,941,242.55, to an amount not to exceed $51,033,719.95.
 
Funds are available in Account 401-50000-645600.
 
Requested, Catherine A. O'Connor, Director of Engineering, WSS:KMF
Recommended, Darlene A. LoCascio, Director of Procurement and Materials Management
Respectfully Submitted, Barbara J. McGowan, Chairman Committee on Procurement