To watch the live meeting proceedings, please refresh this page at the scheduled meeting time, a link labeled "In Progress" will appear under the Video column
File #: 15-0625    Version: 1
Type: Agenda Item Status: Adopted
File created: 6/5/2015 In control: Procurement Committee
On agenda: 6/18/2015 Final action: 6/18/2015
Title: Authority to advertise Contract 15-901-21 Furnish, Deliver and Install Four Sacrificial Deep Anode Ground Beds for the Cathodic Protection System Located at the Mainstream Pumping Station, estimated cost $460,000.00, Account 201-50000-645700, Requisition 1396951
TRANSMITTAL LETTER FOR BOARD MEETING OF JUNE 18, 2015
 
COMMITTEE ON PROCUREMENT
 
Mr. David St. Pierre, Executive Director
 
Title
Authority to advertise Contract 15-901-21 Furnish, Deliver and Install Four Sacrificial Deep Anode Ground Beds for the Cathodic Protection System Located at the Mainstream Pumping Station, estimated cost $460,000.00, Account 201-50000-645700, Requisition 1396951
Body
 
Dear Sir:
 
Contract documents and specifications have been prepared for Contract 15-901-21 Furnish, Deliver and Install Four Sacrificial Deep Anode Ground Beds for the Cathodic Protection System Located at the Mainstream Pumping Station, at the request of the Maintenance and Operations Department.
 
The purpose of this contract is to restore the full performance of the cathodic protection system for the Mainstream Pumping Station. This work will protect valuable underground equipment and structures from harmful electric currents.
The estimated cost for this contract is $460,000.00.
 
The bid deposit for this contract is $23,000.00.
 
The Multi-Project Labor Agreement (MPLA) will be included in this contract.
 
The Affirmative Action Interim Ordinance Appendix D will be included in this contract. The type of work to be performed under the contract is within the "Electrical" category for establishing Minority-owned Business Enterprises (MBE), Women-owned Business Enterprises (WBE) and/or Small Business Enterprises (SBE) utilization goals.  The MBE, WBE and/or SBE utilization goals for this contract are: 13% MBE, 7% WBE, and 10 %SBE.
 
It is estimated that this contract will employ five to seven personnel.
 
The tentative schedule for this contract is as follows:
Advertise                  August 5, 2015
Bid Opening                  August 25, 2015
Award                        September 17, 2015
Completion                  December 31, 2015
 
Funds are available in Account 201-50000-654700.
 
In view of the foregoing, it is recommended that the Director of Procurement and Materials Management be authorized to advertise Contract 15-901-21.
 
Requested, Manju Prakash Sharma, Director of Maintenance and Operations, AQ:SO'C:MAG:CM:NRE
Recommended, Darlene A. LoCascio, Director of Procurement and Materials Management
Respectfully Submitted, Barbara J. McGowan, Chairman Committee on Procurement
Disposition of this agenda item will be documented in the official Regular Board Meeting Minutes of the Board of Commissioners for June 18, 2015