File #: 15-0942    Version: 1
Type: Agenda Item Status: Adopted
File created: 8/20/2015 In control: Procurement Committee
On agenda: 9/3/2015 Final action: 9/3/2015
Title: Authority to advertise Contract 15-721-21 Devon Instream Aeration Station Air Main Replacement, estimated cost $360,000.00, Account 201-50000-645700, Requisition 1388402

TRANSMITTAL LETTER FOR BOARD MEETING OF SEPTEMBER 3, 2015

 

COMMITTEE ON PROCUREMENT

 

Mr. David St. Pierre, Executive Director

 

Title

Authority to advertise Contract 15-721-21 Devon Instream Aeration Station Air Main Replacement, estimated cost $360,000.00, Account 201-50000-645700, Requisition 1388402

Body

 

Dear Sir:

 

Contract documents and specifications have been prepared for Contract 15-721-21 Devon Instream Aeration Station Air Main Replacement, at the request of the Maintenance and Operations Department.

 

The existing air main has corroded and holes allow groundwater to enter the pipe and block the diffusers. The groundwater must be removed by pumping in order for the station to operate. Repairs were attempted but cannot be completed because the pipe walls are now corroded to the point where they are too thin to allow welding or other repairs. It is estimated that in as little as one to two years, the station will no longer be operable if the air main is not replaced. The purpose of this contract is to abandon and fill the existing air main and install a new air main to restore proper operation.

 

The estimated cost for this contract is $360,000.00.

 

The contract specifications require that all work be completed within 90 days after approval of the Contractor's Bond.

 

The bid deposit for this contract is $18,000.00.

 

The Multi-Project Labor Agreement (MPLA) will be included in this contract.

 

The Affirmative Action Ordinance, Revised Appendix D, will be included in this contract. The work under this contract is classified “Mechanical.” The MBE, WBE and/or SBE utilization goals for this contract are 20% MBE, 9% WBE and 10% SBE.

 

The tentative schedule for this contract is as follows:

Advertise                                                               September 9, 2015

Bid Opening                                                               October 6, 2015

Award                                                                                    November 5, 2015

Completion                                                               December 31, 2015

 

Funds are available in Account 201-50000-645700.

 

In view of the foregoing, it is recommended that the Director of Procurement and Materials Management be authorized to advertise Contract 15-721-21.

 

Requested, Manju Prakash Sharma, Director of Maintenance and Operations, AQ:SO’C:MAG:JR:JK

Recommended, Darlene A. LoCascio, Director of Procurement and Materials Management

Respectfully Submitted, Barbara J. McGowan, Chairman Committee on Procurement