TRANSMITTAL LETTER FOR BOARD MEETING OF OCTOBER 1, 2015
COMMITTEE ON PROCUREMENT
Mr. David St. Pierre, Executive Director
Title
Report of bid opening of Tuesday, September 15, 2015
Body
Dear Sir:
Bids were received and opened on 9/15/2015 for the following contracts:
CONTRACT 15-036-11 FURNISH AND DELIVER SALT AND CALCIUM CHLORIDE TO VARIOUS LOCATIONS FOR A ONE (1) YEAR PERIOD
LOCATION: VARIOUS
ESTIMATE: $28,000.00
GROUP: TOTAL
MARCO SUPPLY COMPANY $40,479.75
ATLAS & ASSOCIATES, INC. $49,480.00
BIDDERS NOTIFIED: 87 PLANHOLDERS: 19
CONTRACT 15-655-11 MANHOLE AND INFRASTRUCTURE REPAIRS
LOCATION: VARIOUS
ESTIMATE: $625,000.00
GROUP: TOTAL
PAN-OCEANIC ENGINEERING CO., INC. $1,062,450.00
BIDDERS NOTIFIED: 690 PLANHOLDERS: 32
CONTRACT 15-901-21 FURNISH, DELIVER AND INSTALL FOUR SACRIFICIAL DEEP ANODE GROUND BEDS FOR THE CATHODIC PROTECTION SYSTEM LOCATED AT THE MAINSTREAM PUMPING STATION
LOCATION: MAINSTREAM PUMPING STATION
ESTIMATE: $460,000.00
GROUP: TOTAL
CORRPRO COMPANIES, INC. $404,850.00
CATHODIC PROTECTION MANAGEMENT, INC. $459,779.00
BIDDERS NOTIFIED: 163 PLANHOLDERS: 25
Respectfully Submitted, Darlene A. LoCascio, Director of Procurement and Materials Management