TRANSMITTAL LETTER FOR BOARD MEETING OF OCTOBER 15, 2015
COMMITTEE ON PROCUREMENT
Mr. David St. Pierre, Executive Director
Title
Report of bid opening of Tuesday, October 6, 2015
Body
Dear Sir:
Bids were received and opened on 10/6/2015 for the following contracts:
CONTRACT 06-155-3S SALT CREEK INTERCEPTING SEWER 2 REHABILITATION, SSA
LOCATION: STICKNEY, IL
ESTIMATE: $48,050,000.00
GROUP: TOTAL
KENNY CONSTRUCTION COMPANY $43,878,100.00
INSITUFORM TECHNOLOGIES USA $47,424,400.00
SUPER EXCAVATORS, INC. $49,965,000.00
MI-CON, A DIV. OF MICHELS CORPORATION $54,908,563.27
JAY DEE CONTRACTORS, INC. $56,680,000.00
SAK CONSTRUCTION, LLC $57,103,250.00
BIDDERS NOTIFIED: 569 PLANHOLDERS: 71
CONTRACT 15-045-11 PUBLISH INVITATIONS TO BID FOR CONTRACTS, LEGAL NOTICES FOR ORIGINAL ENTRANCE AND PROMOTIONAL CIVIL SERVICE EXAMINATIONS, AND OTHER LEGAL NOTICES FOR A ONE-YEAR PERIOD
LOCATION: MOB
ESTIMATE: $84,000.00
GROUP: TOTAL
SUN-TIMES MEDIA PRODUCTIONS LLC $76,260.00
THE LAWNDALE NEWS $113,484.00
TRIBUNE PUBLISHING COMPANY LLC $139,500.00
CHICAGO DEFENDER PUBLISHING COMPANY. LLC. $279,000.00
BIDDERS NOTIFIED: 42 PLANHOLDERS: 9
CONTRACT 15-063-11 FURNISH AND DELIVER V-BELTS AND CONVEYOR BELTS TO VARIOUS LOCATIONS FOR A ONE-YEAR PERIOD
LOCATION: VARIOUS
ESTIMATE: $30,000.00
GROUP: A V-BELTS
ACE HOSE & RUBBER COMPANY $3,943.29
ACCENT BEARINGS COMPANY, INC. $4,189.33
CHICAGO CHAIN & TRANSMISSION COMPANY, INC. $4,498.48
MOTION INDUSTRIES, INC. $4,559.09
CONVEYALL INDUSTRIAL SUPPLY, INC. $5,318.55
BROOKAIRE COMPANY LLC $5,320.07
BEARINGS & INDUSTRIAL SUPPLY CO., INC. $5,544.96
R & R EQUIPMENT PLUS, INC. $5,772.90
R & R EQUIPMENT PLUS, INC. $6,122.77
RUSSO POWER EQUIPMENT, INC. $7,288.11
GROUP: B CONVEYOR BELTS
BEARINGS & INDUSTRIAL SUPPLY CO., INC. $26,883.87
MOTION INDUSTRIES, INC. $28,058.40
QUARRY SUPPLY, INC. $28,207.00
ACE HOSE & RUBBER COMPANY $31,561.80
BELCON/REGIS GROUP, INC. $40,746.50
CONVEYALL INDUSTRIAL SUPPLY, INC. $59,646.93
CHICAGO CHAIN & TRANSMISSION COMPANY, INC. $60,506.86
BIDDERS NOTIFIED: 166 PLANHOLDERS: 26
CONTRACT 15-607-21 FURNISH AND DELIVER STATION BATTERIES TO THE STICKNEY AND O'BRIEN WATER RECLAMATION PLANTS, AND THE NORTH BRANCH PUMPING STATION
LOCATION: VARIOUS
ESTIMATE: $210,000.00
GROUP: TOTAL
NO BIDS RECEIVED
BIDDERS NOTIFIED: 890 PLANHOLDERS: 26
CONTRACT 15-711-21 PROCESS CONTROL BUILDING RESTORATION AT THE O'BRIEN WATER RECLAMATION PLANT
LOCATION: TERRENCE J. O'BRIEN WATER RECLAMATION PLANT
ESTIMATE: $525,000.00
GROUP: TOTAL
RESTORE MASONRY, LLC $495,925.00
BIDDERS NOTIFIED: 762 PLANHOLDERS: 37
CONTRACT 15-721-21 DEVON INSTREAM AERATION STATION AIR MAIN REPLACEMENT
LOCATION: SKOKIE, IL
ESTIMATE: $360,000.00
GROUP: TOTAL
MORRISON CONSTRUCTION COMPANY, INC. $353,060.00
INDEPENDENT MECHANICAL INDUSTRIES, INC. $354,000.00
IHC CONSTRUCTION COMPANIES, .LLC $559,000.00
BIDDERS NOTIFIED: 733 PLANHOLDERS: 24
CONTRACT 15-802-21 FURNISH, DELIVER AND INSTALL A HYDRAULIC OPERATOR AT TARP GATE STRUCTURE NUMBER 1 IN THE CALUMET SERVICE AREA
LOCATION: CALUMET
ESTIMATE: $1,500,000.00
GROUP: TOTAL
ORNELAS CONSTRUCTION COMPANY $1,324,000.00
INDEPENDENT MECHANICAL INDUSTRIES, INC. $1,459,238.00
JAY DEE CONTRACTORS, INC. $1,521,200.00
IHC CONSTRUCTION COMPANIES, .LLC $1,708,000.00
BIDDERS NOTIFIED: 534 PLANHOLDERS: 21
CONTRACT 15-813-22 REHABILITATION OF BUILDINGS AT THE PRAIRIE PLAN SITE IN FULTON COUNTY, ILLINOIS (RE-BID)
LOCATION: FULTON COUNTY
ESTIMATE: $250,000.00
GROUP: TOTAL
CAD CONSTRUCTION, INC. $230,000.00
HOLTHAUS COMPANIES, INC. $263,850.00
BIDDERS NOTIFIED: 1069 PLANHOLDERS: 18
Respectfully Submitted, Darlene A. LoCascio, Director of Procurement and Materials Management