File #: 15-0884    Version: 1
Type: Agenda Item Status: Adopted
File created: 7/24/2015 In control: Procurement Committee
On agenda: 8/6/2015 Final action: 8/6/2015
Title: Authority to advertise Contract 15-607-21 Furnish and Deliver Station Batteries to the Stickney and  O’Brien Water Reclamation Plants, and the North Branch Pumping Station, estimated cost $210,000.00, Accounts 201-50000-645600/645650, Requisition 1401466

 TRANSMITTAL LETTER FOR BOARD MEETING OF AUGUST 6, 2015

 

COMMITTEE ON PROCUREMENT

 

Mr. David St. Pierre, Executive Director

 

Title

Authority to advertise Contract 15-607-21 Furnish and Deliver Station Batteries to the Stickney and  O’Brien Water Reclamation Plants, and the North Branch Pumping Station, estimated cost $210,000.00, Accounts 201-50000-645600/645650, Requisition 1401466

Body

 

Dear Sir:

 

Contract documents and specifications have been prepared to Furnish and Deliver Station Batteries to the Stickney and O’Brien Water Reclamation Plants, and the North Branch Pumping Station, at the request of the Maintenance and Operations Department.

 

The purpose of this contract is to furnish and deliver station batteries to the Stickney and O’Brien Water Reclamation Plants, and the North Branch Pumping Station. The units supply DC power to the tripping and charging circuits, protective relays, and monitoring devices for the switchgear at those locations. The three DC battery line-ups have been experiencing premature problems where the internal plates have been expanding and dislodging the post seals of the battery cells, reducing the service life from twenty years to ten years.

 

The estimated cost for this contract is $210,000.00.

 

The bid deposit for this contract is $10,500.00.

 

The Multi-Project Labor Agreement is not included in this contract because it is a furnish and deliver contract for equipment.

 

The Affirmative Action Ordinance, Revised Appendix D, will not be included in this contract because it is a furnish and deliver contract.

 

The tentative schedule for this contract is as follows:

Advertise                     August 26, 2015

Bid Opening                     September 15, 2015

Award                     October 1, 2015

Completion                      December 31, 2015

 

Funds are available in Accounts 201-50000-645600/645650.

 

In view of the foregoing, it is recommended that the Director of Procurement and Materials Management be authorized to advertise Contract 15-607-21.

 

Requested, Manju Prakash Sharma, Director of Maintenance and Operations, AQ:SO’C:MAG:JR

Recommended, Darlene A. LoCascio, Director of Procurement and Materials Management

Respectfully Submitted, Barbara J. McGowan, Chairman Committee on Procurement