To watch the live meeting proceedings, please refresh this page at the scheduled meeting time, a link labeled "In Progress" will appear under the Video column
File #: 15-1339    Version: 1
Type: Agenda Item Status: Adopted
File created: 11/20/2015 In control: Procurement Committee
On agenda: 12/3/2015 Final action: 12/3/2015
Title: Authority to advertise Contract 16-611-11 Repairs and Alterations to Various Water Reclamation Facilities in the Stickney Service Area and Other Installations, estimated cost $11,826,600.00, Accounts 101-67000/68000/69000-612600/612650, Requisitions 1406549, 1407120 and 1407111

TRANSMITTAL LETTER FOR BOARD MEETING OF DECEMBER 3, 2015

 

COMMITTEE ON Procurement

 

Mr. David St. Pierre, Executive Director

 

Title

Authority to advertise Contract 16-611-11 Repairs and Alterations to Various Water Reclamation Facilities in the Stickney Service Area and Other Installations, estimated cost $11,826,600.00, Accounts 101-67000/68000/69000-612600/612650, Requisitions 1406549, 1407120 and 1407111

Body

 

Dear Sir:

 

Contract documents and specifications have been prepared for Contract 16-611-11 Repairs and Alterations to Various Water Reclamation Facilities in the Stickney Service Area and Other Installations, for a two-year period, at the request of the Maintenance and Operations Department.

 

The purpose of this contract is to procure approximately 142,195 labor hours of various skilled and unskilled trades. The required classifications of trades include: boilermakers, bricklayers, carpenters, electricians, instrument mechanics, hoisting engineers, machinists, painters, pipefitters, pipe coverers, plumbers, sheet metal workers, structural ironworkers, architectural ironworkers, laborers and truck drivers. These labor services will be used for performing repairs and alterations at the Stickney, Calumet and North Service Areas and other installations during the period from approximately March 17, 2016, through December 31, 2017.

 

The estimated cost for this contract is $11,826,600.00. The estimated 2016 and 2017 expenditures are $6,146,600.00 and $5,680,000.00 respectively.

 

The bid deposit for this contract is $335,000.00.

 

The contract specifications require that the contractor commence work upon approval of the contractor’s bond and all work shall be completed by December 31, 2017.

 

The Multi-Project Labor Agreement (MPLA) will be included in this contract.

 

The Affirmative Action Ordinance, Revised Appendix D will be included in this contract. The type of work to be performed under the contract is within the “General Construction” category for establishing Minority-owned Business Enterprises (MBE), Women-owned Business Enterprises (WBE) and Small Business Enterprises (SBE) utilization goals. The WBE, MBE and SBE utilization goals for this contract are: 20% Minority Business Enterprises (MBE), 9% Women’s Business Enterprises (WBE) and 10% Small Business Enterprises (SBE).

 

The tentative schedule for this contract is as follows:

Advertise                     January 6, 2016

Bid Opening                     February 2, 2016

Award                     March 3, 2016

Completion                      December 31, 2017

 

Funds are being requested in 2016 and 2017 in Accounts 101-67000/68000/69000-612600/612650, and are contingent on the Board of Commissioners’ approval of the District’s budget for those years.

 

In view of the foregoing, it is recommended that the Director of Procurement and Materials Management be authorized to advertise Contract 16-611-11.

 

Requested, Manju Prakash Sharma, Director of Maintenance & Operations, AQ:SO’C:MAG:JR

Recommended, Darlene A. LoCascio, Director of Procurement and Materials Management

Respectfully Submitted, Barbara J. McGowan, Chairman Committee on Procurement

Disposition of this agenda item will be documented in the official Regular Board Meeting Minutes of the Board of Commissioners for December 3, 2015