File #: 17-0120    Version: 1
Type: Agenda Item Status: Adopted
File created: 1/24/2017 In control: Real Estate Development Committee
On agenda: 2/2/2017 Final action: 2/2/2017
Title: Authority to amend Board Order of October 20, 2016, authorizing the grant of a 25-year, 2,624.20’ x 20’ (52,484 sq. ft.) non-exclusive easement to Commonwealth Edison Company to install, maintain, operate, repair, replace and remove electrical transmission lines and facilities on a portion of District Main Channel Parcels 19.01 and 19.04 in Will County, Illinois, to reflect a reduced area of 21,090 sq. ft. on a portion of Main Channel Parcel 19.04.
Attachments: 1. Aerial Map.Parcel 19.04.pdf

TRANSMITTAL LETTER FOR BOARD MEETING OF FEBRUARY 2, 2017

 

COMMITTEE ON REAL ESTATE

 

Mr. David St. Pierre, Executive Director

 

Title

Authority to amend Board Order of October 20, 2016, authorizing the grant of a 25-year, 2,624.20’ x 20’ (52,484 sq. ft.) non-exclusive easement to Commonwealth Edison Company to install, maintain, operate, repair, replace and remove electrical transmission lines and facilities on a portion of District Main Channel Parcels 19.01 and 19.04 in Will County, Illinois, to reflect a reduced area of 21,090 sq. ft. on a portion of Main Channel Parcel 19.04.

Body

 

Dear Sir:

 

At its meeting of October 20, 2016, the Board of Commissioners (“Board”) authorized the grant of a 25-year, 2,624.20’ x 20’ (52,484 sq. ft.) non-exclusive easement to Commonwealth Edison Company (“ComEd”) to install, maintain, operate, repair and remove electrical transmission lines to provide additional electrical services to the U.S. Army Corps of Engineers’ (“Corps”) aquatic nuisance species barriers on a portion of District Main Channel Parcels 19.01 and 19.04 in Will County, Illinois, for an initial annual fee of $5,000.00.

 

Thereafter, ComEd re-evaluated its land use needs for this project and advised that only a 21,090 sq. ft. area on Main Channel Parcel 19.04 instead of 52,484 sq. ft. area on Parcels 19.01 and 19.04 is necessary to provide additional electrical services to the Corps’ aquatic nuisance species barriers project.  The initial annual fee and all other aspects of the Board’s October 20, 2016 Orders shall remain as originally approved.

 

It is requested that the Executive Director recommend that the Board of Commissioners amend its Orders of October 20, 2016, authorizing the grant of a 25-year, 2,624.20’ x 20’ (52,484 sq. ft.) non-exclusive easement to Commonwealth Edison Company to install, maintain, operate, repair, replace and remove electrical transmission lines and facilities on a portion of District Main Channel Parcels 19.01 and 19.04 in Will County, Illinois, to reflect a reduced area of 21,090 sq. ft. on a portion of District Main Channel Parcel 19.04.

 

Requested, Ronald M. Hill, General Counsel, RMH:STM:MM

Recommended, David St. Pierre, Executive Director

Respectfully Submitted, David J. Walsh, Chairman Committee on Real Estate Development

Disposition of this agenda item will be documented in the official Regular Board Meeting Minutes of the Board of Commissioners for February 2, 2017

 