To watch the live meeting proceedings, please refresh this page at the scheduled meeting time, a link labeled "In Progress" will appear under the Video column
File #: 17-0190    Version: 1
Type: Agenda Item Status: Adopted
File created: 2/9/2017 In control: Finance Committee
On agenda: 2/16/2017 Final action: 2/16/2017
Title: Authority to add Project 17-903-41, Elevator Improvements at the Mainstream Pumping Station, to the Capital Improvements Bond Fund, estimated cost of the project is $245,000.00.

TRANSMITTAL LETTER FOR BOARD MEETING OF FEBRUARY 16, 2017

 

COMMITTEE ON FINANCE

 

Mr. David St. Pierre, Executive Director

 

Title

Authority to add Project 17-903-41, Elevator Improvements at the Mainstream Pumping Station, to the Capital Improvements Bond Fund, estimated cost of the project is $245,000.00.

Body

 

Dear Sir:

 

Authority is requested to add Project 17-903-41, Elevator Improvements at the Mainstream Pumping Station, to the Capital Improvements Bond Fund at the request of the Maintenance and Operations Department.

 

The purpose of the project is to provide all necessary labor, supervision, tools, equipment, materials and appurtenances to rehabilitate the north and south vent elevators at the Mainstream Pumping Station.

 

The project consists of performing structural, mechanical and electrical repairs to the elevators, thus returning to service and extending the useful life of the elevators at the Mainstream Pumping Station Facilities. The estimated cost of this project is $245,000.00.

 

Requested, John P. Murray, Director of Maintenance and Operations, BAP:SO’C:MAG:JR

Respectfully Submitted, Frank Avila, Chairman Committee on Finance

Disposition of this agenda item will be documented in the official Regular Board Meeting Minutes of the Board of Commissioners for February 16, 2017