File #: 17-0761    Version: 1
Type: Agenda Item Status: Adopted
File created: 7/20/2017 In control: Procurement Committee
On agenda: 8/3/2017 Final action: 8/3/2017
Title: Authority to advertise Contract 17-705-21, Rehabilitate One Raw Sewage Pump Rotating Assembly at the O’Brien Water Reclamation Plant, Estimated cost $200,000.00, Account 201-50000-645600, Requisition 1456115

TRANSMITTAL LETTER FOR BOARD MEETING OF AUGUST 3, 2017

 

COMMITTEE ON PROCUREMENT

 

Mr. David St. Pierre, Executive Director

 

Title

Authority to advertise Contract 17-705-21, Rehabilitate One Raw Sewage Pump Rotating Assembly at the O’Brien Water Reclamation Plant, Estimated cost $200,000.00, Account 201-50000-645600, Requisition 1456115

Body

 

Dear Sir:

 

Contract documents and specifications have been prepared for Contract 17-705-21, Rehabilitate One Raw Sewage Pump Rotating Assembly at the O’Brien Water Reclamation Plant, at the request of the Maintenance and Operations Department.

 

The purpose of this contract is to perform the complete rehabilitation of one 65 MGD main raw sewage pump rotating assembly at the O’Brien Water Reclamation Plant. The work will include sandblasting, inspection, machining, and weld repair of the pump impeller as well as fabrication of a new pump shaft, casing rings, impeller rings and shaft sleeves. This will be followed by reassembly and dynamic balancing according to ISO Standards.

 

The estimated cost of this contract is $200,000.00. The estimated 2017 and 2018 expenditures are $150,000.00 and $50,000.00, respectively.

 

The bid deposit for this contract is $10,000.00.

 

The Multi-Project Labor Agreement (MPLA) will not be included in this contract because the rebuild work will be performed offsite at the Contractor’s facility.

 

The Affirmative Action Ordinance, Revised Appendix D will not be included in this contract because the required services do not provide practical or cost-effective opportunities for direct or indirect subcontracting.

 

The tentative schedule for this contract is as follows:

Advertise                     September 6, 2017

Bid Opening           September 26, 2017

Award                              October 19, 2017

Completion              December 31, 2018

 

Funds are available in Account 201-50000-645600.

 

In view of the foregoing, it is recommended that the Director of Procurement and Materials Management be authorized to advertise Contract 17-705-21.

 

Requested, John P. Murray, Director of Maintenance and Operations, BAP:SO’C:MAG:JR:JMC:BK:AJP

Recommended, Darlene A. LoCascio, Director of Procurement and Materials Management     

Respectfully Submitted, Barbara J. McGowan, Chairman Committee on Procurement