File #: 17-0765    Version: 1
Type: Agenda Item Status: Adopted
File created: 7/20/2017 In control: Finance Committee
On agenda: 8/3/2017 Final action: 8/3/2017
Title: Authority to add Project 17-712-21 Furnish and Deliver Two Submersible Pumps to the O’Brien Water Reclamation Plant, to the Construction Fund, estimated cost of the project is $80,000.00

TRANSMITTAL LETTER FOR BOARD MEETING OF AUGUST 3, 2017

 

COMMITTEE ON FINANCE

 

Mr. David St. Pierre, Executive Director

 

Title

Authority to add Project 17-712-21 Furnish and Deliver Two Submersible Pumps to the O’Brien Water Reclamation Plant, to the Construction Fund, estimated cost of the project is $80,000.00

Body

 

Dear Sir:

 

Authority is requested to add Project 17-712-21 Furnish and Deliver Two Submersible Pumps to the O’Brien Water Reclamation Plant, to the Construction Fund, at the request of the Maintenance and Operations Department.

 

The project consists of procuring two new submersible pumps and appurtenances to replace the existing process water pumps w at the O’Brien Water Reclamation Plant. The existing process water pumps have proven to be unreliable and problematic. The new pumps will have a semi-open channel impeller, which will increase pumping efficiency from 38% to 62%, resulting in an annual energy savings of approximately $16,000.00.

 

The estimated cost of the project is $80,000.00.

 

Requested, John P. Murray, Director of Maintenance and Operations, BAP:SO’C:MAG:JR:JMC:MWK

Respectfully Submitted, Frank Avila, Chairman Committee on Finance