File #: 17-0850    Version: 1
Type: Report Status: Filed
File created: 8/18/2017 In control: Engineering Committee
On agenda: 8/31/2017 Final action: 8/31/2017
Title: Report on change orders authorized and approved by the Director of Engineering during the months of June and July 2017
Attachments: 1. Attachment 1 CO Report June and July 2017 $10,000, 2. Attachment 2 CO Report June and July 2017 5% Contingency, 3. Attachment 3 CO Report June and July 2017 Summary

TRANSMITTAL LETTER FOR BOARD MEETING OF AUGUST 31, 2017

 

COMMITTEE ON ENGINEERING

 

Mr. David St. Pierre, Executive Director

 

Title

Report on change orders authorized and approved by the Director of Engineering during the months of June and July 2017

Body

 

Dear Sir:

 

One change order was approved by the Director of Engineering that cumulatively, but not individually, increased or decreased the value of the contract by $10,000.00 or less during June and July 2017.  The contract and related data is listed in Attachment 1

 

Twenty-two change orders were approved by the Director of Engineering on contracts with a 5% contingency provision for errors and omissions and unforeseen circumstances, for an increase or decrease of $100,000.00 or less during June and July 2017.  The contracts and related data are listed in Attachment 2.

 

Please advise the undersigned if additional information is required.

 

Respectfully Submitted, Marcella V. Landis, Acting Director of Engineering, MVL:JFK

 