File #: 17-1185    Version: 1
Type: Agenda Item Status: Adopted
File created: 11/3/2017 In control: Real Estate Development Committee
On agenda: 11/16/2017 Final action: 11/16/2017
Title: Authority to enter into a Utility Relocation Agreement with Commonwealth Edison Company to relocate existing electrical transmission lines and facilities on a parcel of real estate recently acquired by the District as part of the construction of the Addison Creek Reservoir (Contract 11-186-3F) located at 2795 West Washington Boulevard in Bellwood, Illinois.  Consideration shall be a nominal fee of $10.00
Attachments: 1. Aerial Map.Addison Creek Reservoir Site (ComEd).pdf

TRANSMITTAL LETTER FOR BOARD MEETING OF NOVEMBER 16, 2017

 

COMMITTEE ON REAL ESTATE

 

Mr. David St. Pierre, Executive Director

 

Title

Authority to enter into a Utility Relocation Agreement with Commonwealth Edison Company to relocate existing electrical transmission lines and facilities on a parcel of real estate recently acquired by the District as part of the construction of the Addison Creek Reservoir (Contract 11-186-3F) located at 2795 West Washington Boulevard in Bellwood, Illinois.  Consideration shall be a nominal fee of $10.00

Body

 

Dear Sir:

 

The District has requested that Commonwealth Edison Company (“ComEd”) enter into a Utility Relocation Agreement (“URA”) with the District that would provide for the relocation of certain existing ComEd electrical transmission lines and facilities (“existing electrical facilities”).  The existing electrical facilities are located, pursuant to ComEd’s easement, on a parcel of real estate recently acquired by the District through condemnation proceedings as part of the construction of the Addison Creek Reservoir (“Reservoir”) (Contract 11-186-3F).  The parcel is located at 2795 West Washington Boulevard in Bellwood, Illinois.

 

The existing electrical facilities provide electricity to the surrounding commercially developed area.  Under the URA, the existing electrical facilities would be removed and the new electrical facilities would be located near the northern and eastern boundary of the Reservoir area.  The relocated easement area comprises approximately 14,326 square feet.  The Engineering Department has confirmed that such relocation is consistent with the District’s plans for the construction, operation and maintenance of the Reservoir.

 

A nominal fee of $10.00 is recommended in this instance as ComEd had an existing no-fee perpetual easement through the acquired property.  Additionally, the URA will provide that the District will pay a utility relocation fee of $236,553.20 to ComEd, which the Board previously authorized at its meeting of October 19, 2017.  In exchange, under the URA, ComEd will relinquish any existing easement rights it has on this parcel.  This will result in considerable savings to the District since, without such an agreement, the District would have to initiate condemnation proceedings to acquire the easement, and because this is a utility easement, obtain the Illinois Commerce Commission’s approval for the condemnation.

 

It is requested that the Executive Director recommend to the Board of Commissioners that it grant authority to enter into a Utility Relocation Agreement with Commonwealth Edison Company to relocate existing electrical transmission lines and facilities on a parcel of real estate recently acquired by the District as part of the construction of the Addison Creek Reservoir (Contract 11-186-3F) located at 2795 West Washington Boulevard in Bellwood, Illinois.  Consideration shall be a nominal fee of $10.00.

 

It is also requested that the Executive Director recommend to the Board of Commissioners that it authorize and direct the Chairman of the Committee on Finance and the Clerk to execute the Utility Relocation Agreement on behalf of the District after it is approved by the General Counsel as to form and legality.

 

Requested, Susan T. Morakalis, General Counsel, STM:CMM:MLD:vp

Recommended, David St. Pierre, Executive Director

Respectfully Submitted, David J. Walsh, Chairman Committee on Real Estate Development Disposition of this agenda item will be documented in the official Regular Board Meeting Minutes of the Board of Commissioners for November 16, 2017

 