File #: 18-0030    Version: 1
Type: Agenda Item Status: Adopted
File created: 1/5/2018 In control: Procurement Committee
On agenda: 1/18/2018 Final action: 1/18/2018
Title: Authority to decrease Contract 15-802-21, Furnish, Deliver and Install a Hydraulic Operator at TARP Gate Structure Number 1 in the Calumet Service Area, to Ornelas Construction Company, in an amount of $66,924.23 from an amount of $1,324,000.00 to a final amount of $1,257,075.77, Account 201-50000-645600, Purchase Order 5001541

TRANSMITTAL LETTER FOR BOARD MEETING OF JANUARY 18, 2018

 

COMMITTEE ON PROCUREMENT

 

Mr. David St. Pierre, Executive Director

 

Title

Authority to decrease Contract 15-802-21, Furnish, Deliver and Install a Hydraulic Operator at TARP Gate Structure Number 1 in the Calumet Service Area, to Ornelas Construction Company, in an amount of $66,924.23 from an amount of $1,324,000.00 to a final amount of $1,257,075.77, Account 201-50000-645600, Purchase Order 5001541

Body

 

Dear Sir:

 

On November 5, 2015, the Board of Commissioners authorized the Director of Procurement and Materials Management to award Contract 15-802-21, Furnish, Deliver and Install a Hydraulic Operator at TARP Gate Structure Number 1 in the Calumet Service Area, to Ornelas Construction Company, in an amount not to exceed $1,324,000.00. The contract was completed on October 13, 2017.

 

There have been no prior change orders to this Contract.

 

A decrease in contract value is being requested to close out the purchase order.

 

This change order is in compliance with the Illinois Criminal Code since the change is due to circumstances not reasonably foreseeable at the time the contract was signed, and is in the best interest of the District.

 

It is hereby recommended that the Board of Commissioners authorize the Director of Procurement and Materials Management to execute a change order to decrease Contract 15-802-21, in an amount of $66,924.23 (approximately 5.1% of the current contract value) from an amount of $1,324,000.00 to a final amount of $1,257,075.77.

 

Funds will be restored to Account 201-50000-645600.

 

Requested, John P. Murray, Director of Maintenance and Operations, BAP:SO’C:MAG:JR

Recommended, Darlene A. LoCascio, Director of Procurement and Materials Management

Respectfully Submitted, Barbara J. McGowan, Chairman Committee on Procurement

Disposition of this agenda item will be documented in the official Regular Board Meeting Minutes of the Board of Commissioners for January 18, 2018