TRANSMITTAL LETTER FOR BOARD MEETING OF JANUARY 18, 2018
COMMITTEE ON PROCUREMENT
Mr. David St. Pierre, Executive Director
Title
Report of bid opening of Tuesday, January 9, 2018
Body
Dear Sir:
Bids were received and opened on 1/9/2018 for the following contracts:
CONTRACT 11-186-AF DEMOLITION AT ADDISON CREEK RESERVOIR AND THORNTON RESERVOIR
LOCATION: THORNTON COMPOSITE RESERVOIR, CSA
ESTIMATE: $1,115,500.00
GROUP: TOTAL
BECHSTEIN CONSTRUCTION CORPORATION $289,900.00
KLF ENTERPRISES $391,222.00
POULOS, INC. $873,000.00
DYNAMIC WRECKING & EXCAVATION, INC. $1,039,680.00
GALE CONSTRUCTION COMPANY $1,640,278.50
BIDDERS NOTIFIED: 639 PLANHOLDERS: 37
CONTRACT 13-370-3F BUFFALO CREEK RESERVOIR EXPANSION, LAKE COUNTY, ILLINOIS
LOCATION: BUFFALO CREEK
ESTIMATE: $24,300,172.75
GROUP: TOTAL
LAKE COUNTY GRADING COMPANY, LLC $9,678,900.00
BERGER EXCAVATING CONTRACTORS $10,642,000.00
IHC GROUP, INC. $11,629,000.00
LANE CONSTRUCTION CORORATION $11,850,000.00
V3 CONSTRUCTION GROUP $13,995,000.00
JUDLAU CONTRACTING, INC. $16,200,000.00
BIDDERS NOTIFIED: 763 PLANHOLDERS: 92
CONTRACT 18-101-11 PERFORM OLFACTOMETRY ANALYSIS OF ODOROUS GAS SAMPLES
LOCATION: VARIOUS
ESTIMATE: $19,900.00
GROUP: TOTAL
NO BIDS RECEIVED
BIDDERS NOTIFIED: 188 PLANHOLDERS: 12
CONTRACT 18-605-21 FURNISH AND DELIVER STATION BATTERY EQUIPMENT
LOCATION: VARIOUS
ESTIMATE: $275,000.00
GROUP: TOTAL
STORAGE BATTERY SYSTEMS, INC. $196,326.40
STANDBY POWER SYSTEM CONSULTANTS, INC. $255,639.00
ATLAS & ASSOCIATES, INC. $258,800.00
BIDDERS NOTIFIED: 1268 PLANHOLDERS: 30
CONTRACT 18-701-21 FURNISH AND DELIVER TWO DEBRIS BASKETS FOR THE INFLUENT CHANNELS KIRIE WATER RECLAMATION PLANT
LOCATION: KIRIE
ESTIMATE: $200,000.00
GROUP: TOTAL
PUMPING SOLUTIONS, INC. $226,000.00
BIDDERS NOTIFIED: 393 PLANHOLDERS: 11
Respectfully Submitted, Darlene A. LoCascio, Director of Procurement and Materials Management