File #: 18-0375    Version: 1
Type: Agenda Item Status: Adopted
File created: 4/6/2018 In control: Procurement Committee
On agenda: 4/19/2018 Final action: 4/19/2018
Title: Authorization to increase cost estimate and re-advertise Contract 16-126-3SR, Summit Conduit Rehabilitation, SSA, from an estimated cost between $1,520,000.00 and $1,840,000.00 to an estimated cost between $2,375,000.00 and $2,875,000.00, Account 401-50000-645700, Requisition 1474785
Attachments: 1. 16-126-3SR Summit Conduit Rehabilitation, SSA.pdf

TRANSMITTAL LETTER FOR BOARD MEETING OF APRIL 19, 2018

 

COMMITTEE ON PROCUREMENT

 

Mr. David St. Pierre, Executive Director

 

Title

Authorization to increase cost estimate and re-advertise Contract 16-126-3SR, Summit Conduit Rehabilitation, SSA, from an estimated cost between $1,520,000.00 and $1,840,000.00 to an estimated cost between $2,375,000.00 and $2,875,000.00, Account 401-50000-645700, Requisition 1474785

Body

 

Dear Sir:

 

On October 5, 2017, the Board of Commissioners authorized the Director of Procurement and Materials Management to advertise Contract 16-126-3S Summit Conduit Rehabilitation, SSA at an estimated cost between $1,520,000.00 and $1,840,000.00.

 

In response to a public advertisement of October 25, 2017, a bid opening was held on December 5, 2017. No bids were submitted.  Discussions were held with contractors that requested the contract documents to determine why they did not submit bids.  The reasons given included significant risk associate with grouting infiltration, lack of information associated with flow bypassing requirements and uncertainty in the repair method required for patching the previously installed spiral wound PVC pipe.   The revised contract documents now address each of these issues more clearly.

 

In addition, the Engineering Department re-evaluated the cost estimate and adjusted it due to the following:

 

1.                     Increase in quantity for the injection grouting unit price item.

2.                     Reassessed the bypass requirements during rehabilitation of the sewer.

3.                     Increase in labor cost due to work site access difficulty.

 

The revised cost estimate for this contract is between $2,375,000.00 and $2,875,000.00. The estimated cost range will be stated in the advertisement for bids.

 

The revised tentative schedule for this contract is as follows:

 

Advertise                                          May 16, 2018

Bid Opening                                         June 12, 2018

Award                                                               August 2, 2018

Completion                                        July 27, 2019

 

Funds are available in Account 401-50000-645700.

 

In view of the foregoing, it is requested that authority be granted to increase the cost estimate and re-advertise this contract. If approved, the contract will be re-advertised on May 16, 2018.

 

Requested, Catherine A. O’Connor, Director of Engineering, WSS:KMF

Recommended, Darlene A. LoCascio, Director of Procurement and Materials Management

Respectfully Submitted, Barbara J. McGowan, Chairman Committee on Procurement

Disposition of this agenda item will be documented in the official Regular Board Meeting Minutes of the Board of Commissioners for April 19, 2018