File #: 09-0498    Version: 1
Type: Agenda Item Status: Adopted
File created: 3/25/2009 In control: Procurement Committee
On agenda: 4/2/2009 Final action: 4/2/2009
Title: Authority to advertise Contract 09-876-11 Roof Repairs and Replacement in the Calumet Service Area, estimated cost $90,000.00, Account 101-68000-612680, Requisition 1261850

TRANSMITTAL LETTER FOR BOARD MEETING OF APRIL 2, 2009

 

COMMITTEE ON PURCHASING

 

Mr. Richard Lanyon, Executive Director

 

Title

Authority to advertise Contract 09-876-11 Roof Repairs and Replacement in the Calumet Service Area, estimated cost $90,000.00, Account 101-68000-612680, Requisition 1261850

Body

 

Dear Sir:

 

Contract documents and specifications have been prepared for roof repairs and replacement in the Calumet Service Area, at the request of the Maintenance and Operations Department.

 

The purpose of this contract is to procure services to repair roofing systems at various locations within the Calumet Service Area. The services are required to maintain the integrity and safety of the structures, and to minimize their future deterioration.

 

The estimated cost for this contract is $90,000.00. The estimated 2009, 2010 and 2011 expenditures are $40,000.00, $40,000.00 and $10,000.00, respectively.

 

The bid deposit for this contract is $4,500.00.

 

The contract specifications require that all work shall commence upon approval of the contractor’s bond and terminate June 30, 2011, or upon expenditure of available funds, whichever occurs sooner. Liquidated damages are $100.00 for each and every calendar day that the contractor is in default of the time specified for completion of all work. In addition, the contractor agrees to pay $20.00 for each calendar day that the contractor is in default of the time specified for completion of repair work ordered by the Engineer.

 

The Multi-Project Labor Agreement (MPLA) will be included in this contract.

 

Revised Appendix D will not be included in this contract because the Engineer’s estimate is less than the minimum threshold established by Section 4 of the Affirmative Action Ordinance.

 

The tentative schedule for this contract is as follows:

 

Advertise                                          April 22, 2009

Bid Opening                     May 12, 2009

Award                     June 18, 2009

Completion                     June 30, 2011

 

Funds for the current year are available in Account 101-68000-612680.  Funds for subsequent years, 2010 and 2011 are contingent on the Board of Commissioners’ approval of the District’s budget for those years.

 

In view of the foregoing, it is recommended that the Director of Procurement and Materials Management be authorized to advertise Contract 09-876-11.

 

Requested, Osoth Jamjun, Director of Maintenance and Operations, OJ:MPS:SO’C:MAG:KJ

Recommended, Darlene A. LoCascio, Director of Procurement and Materials Management     

Respectfully Submitted, Barbara J. McGowan, Chairman Committee on Purchasing