File #: 18-0639    Version: 1
Type: Agenda Item Status: Adopted
File created: 6/22/2018 In control: Finance Committee
On agenda: 7/12/2018 Final action: 7/12/2018
Title: Authority to add Project 18-804-21 Furnish and Deliver Uninterruptible Power Supplies to the Calumet Water Reclamation Plant, to the Construction Fund, estimated cost of the project is $80,000.00

TRANSMITTAL LETTER FOR BOARD MEETING OF JULY 12, 2018

 

COMMITTEE ON FINANCE

 

Mr. John P. Murray, Acting Executive Director

 

Title

Authority to add Project 18-804-21 Furnish and Deliver Uninterruptible Power Supplies to the Calumet Water Reclamation Plant, to the Construction Fund, estimated cost of the project is $80,000.00

Body

 

Dear Sir:

 

Authority is requested to add Project 18-804-21 Furnish and Deliver Uninterruptible Power Supplies to the Calumet Water Reclamation Plant, to the Construction Fund, at the request of the Maintenance and Operations Department.

 

The project consists of procuring two uninterruptible power supplies (UPS) for the Calumet Water Reclamation Plant. The existing units, which support critical switchgear and Monitoring and Research equipment, are failing and not functioning properly.

 

The estimated cost for the project is $80,000.00.

 

Requested, Brett Garelli, Acting Director of Maintenance and Operations, BAP:SO’C:MAG:JR:JMC

Respectfully Submitted, Frank Avila, Chairman Committee on Finance

Disposition of this agenda item will be documented in the official Regular Board Meeting Minutes of the Board of Commissioners for July 12, 2018