File #: 18-0740    Version: 1
Type: Agenda Item Status: Adopted
File created: 7/19/2018 In control: Procurement Committee
On agenda: 8/2/2018 Final action: 8/2/2018
Title: Authority to advertise Contract 17-134-3M Odor Control Facilities at Sludge Concentration, Southwest Coarse Screen, Overhead Weir, and Post-Centrifuge Building, Stickney Water Reclamation Plant, estimated cost between $14,250,000.00 and $17,250,000.00, Account 401-50000-645650, Requisition 1497121
Attachments: 1. 17-134-3M Project Fact Data Info.pdf

TRANSMITTAL LETTER FOR BOARD MEETING OF AUGUST 2, 2018

 

COMMITTEE ON PROCUREMENT

 

Mr. John P. Murray, Acting Executive Director

 

Title

Authority to advertise Contract 17-134-3M Odor Control Facilities at Sludge Concentration, Southwest Coarse Screen, Overhead Weir, and Post-Centrifuge Building, Stickney Water Reclamation Plant, estimated cost between $14,250,000.00 and $17,250,000.00, Account 401-50000-645650, Requisition 1497121

Body

 

Dear Sir:

 

Contract documents and specifications have been prepared for Contract 17-134-3M Odor Control Facilities at Sludge Concentration, Southwest Coarse Screen, Overhead Weir, and Post-Centrifuge Building, Stickney Water Reclamation Plant.

 

The purpose of this contract is to provide odor control systems to treat odor emissions from Sludge Concentration and WASSTRIP tanks, Overhead Weir, Southwest Coarse Screen and Post-Centrifuge Building. The biofilter units will remove 95% of the hydrogen sulfide (H2S) at the maximum H2S concentration of 20 ppm.

 

The project consists of the following:

 

1.                     Demolition of the Ozonator Building, including the removal of equipment and piping, as shown on the contract documents, to allow for the construction of one of the biofilter systems.

2.                     Removal from the Ozonator Building and reinstallation in the Sludge Biofilter Building of the sodium  hypochlorite tanks and associated equipment for the plant effluent water system.

3.                     Construction of three biofilter odor control systems (two of 38,000 CFM and one of 22,500 CFM),  including in-line fans, associated fiberglass and stainless steel ductwork.

4.                     Construction of structures for odor control equipment and biofilter media bed, including all utilities, electrical and controls.

5.                     Fabrication and installation of covers and ductwork to conduct the air from process areas to the odor control units.

6.                     Installation of fiberglass covers on four WASSTRIP tanks.

7.                     Construction of support columns for overhead ductwork.

 

It is estimated that 150 jobs will be created or saved as a result of award of this contract with an estimated 33,854 man-hours of skilled trades utilized.

 

The estimated cost for this contract is between $14,250,000.00 and $17,250,000.00. The cost range will be stated in the advertisement for bids.

 

The bid deposit for this contract is $600,000.00.

 

The contract specifications require that all work commence 30 calendar days after approval of the contractor’s bond and shall be completed within 650 calendar days after approval of the contractor’s bond. Liquidated damages are $1,000.00 for each calendar day that the contractor is in default of the time specified for failing to achieve substantial work completion and $200.00 for each calendar day that the contractor is in default of the time specified for completion of the entire work.

 

The Multi-Project Labor Agreement will be included in this contract.

 

The Affirmative Action Ordinance, Revised Appendix D will be included in this contract. The type of work to be performed under the contract is within the “General and Heavy Construction” category for establishing Minority-owned Business Enterprises (MBE), Women-owned Business Enterprises (WBE) and/or Small Business Enterprises (SBE) utilization goals. The tailored MBE, WBE and/or SBE utilization goals for this contract are: 15 percent MBE, 7 percent WBE, and 10 percent SBE.

 

The tentative schedule for this contract is as follows:

Advertise                                          August 29, 2018

Bid Opening                                          October 9, 2018

Award                                                               December 6, 2018

Completion                                          September 29, 2020

 

Funds are available in Account 401-50000-645650.

 

In view of the foregoing, it is recommended that the Director of Procurement and Materials Management be authorized to advertise Contract 17-134-3M.

 

Requested, Catherine A. O’Connor, Director of Engineering, ECB:LMK

Recommended, Darlene A. LoCascio, Director of Procurement and Materials Management

Respectfully Submitted, Barbara J. McGowan, Chairman Committee on Procurement

Disposition of this agenda item will be documented in the official Regular Board Meeting Minutes of the Board of Commissioners for August 2, 2018

 

Attachment