File #: 18-0994    Version: 1
Type: Agenda Item Status: Adopted
File created: 9/21/2018 In control: Procurement Committee
On agenda: 10/4/2018 Final action: 10/4/2018
Title: Authority to advertise Contract 18-916-21, Sludge Pump Replacements at the Stickney Water Reclamation Plant, Estimated cost $825,000.00, Account 201-50000-645750, Requisition 1502325

TRANSMITTAL LETTER FOR BOARD MEETING OF OCTOBER 4, 2018

 

COMMITTEE ON PROCUREMENT

 

Mr. John P. Murray, Acting Executive Director

 

Title

Authority to advertise Contract 18-916-21, Sludge Pump Replacements at the Stickney Water Reclamation Plant, Estimated cost $825,000.00, Account 201-50000-645750, Requisition 1502325

Body

 

Dear Sir:

 

Contract documents and specifications have been prepared for Contract 18-916-21, Sludge Pump Replacements at the Stickney Water Reclamation Plant, at the request of the Maintenance and Operations Department.

 

The purpose of this contract is to install both new and previously purchased non-clog centrifugal pumps to replace various screw-centrifugal and rotary lobe pumps in sludge pumping applications throughout the Stickney Plant.

 

The estimated cost of this contract is $825,000.00. The estimated expenditures are $100,000.00 for 2018 and $725,000.00 for 2019.

 

The bid deposit for this contract is $41,250.00.

 

The Multi-Project Labor Agreement (MPLA) will be included in this contract.

 

The Affirmative Action Ordinance, Revised Appendix D will be included in this contract. The type of work to be performed under the contract is within the “Mechanical” category for establishing Minority-owned Business Enterprises (MBE), Women-owned Business Enterprises (WBE) and Small Business Enterprises (SBE) utilization goals. The MBE, WBE and SBE utilization goals for this contract are: 20% MBE, 9% WBE and 10% SBE.

 

The tentative schedule for this contract is as follows:

Advertise                                          October 24, 2018

Bid Opening                                          November 20, 2018

Award                                                               December 20, 2018

Completion                                          December 31, 2019

 

Funds are available in 2018 in Account 201-50000-645750. Funds 2019 are contingent on the Board of Commissioners’ approval of the District’s budget for that year.

 

In view of the foregoing, it is recommended that the Director of Procurement and Materials Management be authorized to advertise Contract 18-916-21.

 

Requested, Sergio Serafino, Acting Director of Maintenance and Operations, BAP:SOC:MAG:JR:JMC:WB

Recommended, Darlene A. LoCascio, Director of Procurement and Materials Management     

Respectfully Submitted, Barbara J. McGowan, Chairman Committee on Procurement

Disposition of this agenda item will be documented in the official Regular Board Meeting Minutes of the Board of Commissioners for October 4, 2018