File #: 18-1122    Version: 1
Type: Report Status: Filed
File created: 10/22/2018 In control: Procurement Committee
On agenda: 11/1/2018 Final action: 11/1/2018
Title: Report of bid opening of Tuesday, October 2, 2018

TRANSMITTAL LETTER FOR BOARD MEETING OF NOVEMBER 1, 2018

 

COMMITTEE ON PROCUREMENT

 

Mr. John P. Murray, Acting Executive Director

 

Title

Report of bid opening of Tuesday, October 2, 2018

Body

 

Dear Sir:

 

Bids were received and opened on 10/2/2018 for the following contracts:

 

CONTRACT 14-108-5F ADDISON CREEK STREAMBANK STABILIZATION PROJECTS NORTHLAKE AND NORTH RIVERSIDE IL

LOCATION:  NORTHLAKE AND NORTH RIVERSIDE

ESTIMATE:  $1,146,085.70

GROUP: TOTAL 

                     COPENHAVER CONSTRUCTION, INC.                     $1,426,000.00

                     INDUSTRIA, INC.                     $1,546,000.00

                     RAUSCH INFRASTRUCTURE LLC                     $1,547,000.00

                     EARTH WERKS LAND IMPROVEMENT & DEVELOPMENT                     $1,950,000.00                      

 

                     BIDDERS NOTIFIED:  588                     PLANHOLDERS:  60

 

Respectfully Submitted, Darlene A. LoCascio, Director of Procurement and Materials Management