Title: Report on change orders authorized and approved by the Director of Engineering during the month of December 2018
Attachments: 1. Attachment 1 CO Report December 2018 2018 5% Contingency.pdf, 2. Attachment 2 CO Status Report December 2018.pdf

TRANSMITTAL LETTER FOR BOARD MEETING OF JANUARY 24, 2019

 

COMMITTEE ON ENGINEERING

 

Mr. Brian A. Perkovich, Executive Director

 

Title

Report on change orders authorized and approved by the Director of Engineering during the month of December 2018

Body

 

Dear Sir:

 

Four change orders were approved by the Director of Engineering on contracts with a 5% contingency provision for errors and omissions and unforeseen circumstances, for an increase or decrease of $100,000.00 or less during December 2018.  The contracts and related data are listed in Attachment 1.

 

Please advise the undersigned if additional information is required.

 

Respectfully Submitted, Catherine A. O’Connor, Director of Engineering, MVL

 