To watch the live meeting proceedings, please refresh this page at the scheduled meeting time, a link labeled "In Progress" will appear under the Video column
File #: 19-0165    Version: 1
Type: Agenda Item Status: Deleted
File created: 2/8/2019 In control: Finance Committee
On agenda: 2/21/2019 Final action: 2/21/2019
Title: Authority to add Project 19-614-21 Furnish and Deliver Closed Circuit Television Cameras to the Stickney and Calumet Water Reclamation Plants, to the Construction Fund, estimated cost of the project is $62,000.00

TRANSMITTAL LETTER FOR BOARD MEETING OF FEBRUARY 21, 2019

 

COMMITTEE ON FINANCE

 

Mr. Brian A. Perkovich, Executive Director

 

Title

Authority to add Project 19-614-21 Furnish and Deliver Closed Circuit Television Cameras to the Stickney and Calumet Water Reclamation Plants, to the Construction Fund, estimated cost of the project is $62,000.00

Body

 

Dear Sir:

 

Authority is requested to add Project 19-614-21 Furnish and Deliver Closed Circuit Television Cameras to the Stickney and Calumet Water Reclamation Plants, to the Construction Fund, at the request of the Maintenance and Operations Department.

 

The project consists of procuring four replacement, explosion-proof, analog cameras that will be used to monitor the coarse screens at the Stickney and Calumet Water Reclamation Plants. The existing fourteen year-old units have either failed or no longer function properly.

 

The estimated cost for the project is $62,000.00.

 

Requested, John P. Murray, Director of Maintenance and Operations, SO’C:MAG:JR:NRE

Respectfully Submitted, Frank Avila, Chairman Committee on Finance

Disposition of this agenda item will be documented in the official Regular Board Meeting Minutes of the Board of Commissioners for February 21, 2019