TRANSMITTAL LETTER FOR BOARD MEETING OF DECEMBER 5, 2019
COMMITTEE ON PROCUREMENT
Mr. Brian A. Perkovich, Executive Director
Title
Report of bid opening of Tuesday, November 19, 2019
Body
Dear Sir:
Bids were received and opened on 11/19/2019 for the following contracts:
CONTRACT 15-266-4H3 ODOR CONTROL SYSTEMS AT TWO TARP SHAFTS AND DECOMMISSIONING OF THE THORNTON TRANSITIONAL RESERVOIR, CALUMET SERVICE AREA
LOCATION: CALUMET
ESTIMATE: $14,598,000.00
GROUP: TOTAL
KENNY CONSTRUCTION COMPANY $19,329,500.00
RAUSCH INFRASTRUCTURE, LLC $20,281,000.00
IHC CONSTRUCTION COMPANIES, LLC $28,870,000.00
BIDDERS NOTIFIED: 615 PLANHOLDERS: 54
CONTRACT 20-100-11 COLLECTION, SHIPMENT, AND ANALYSIS OF WATER SAMPLES FROM THE THORNTON COMPOSITE RESERVOIR AND MONITORING WELLS AND ANALYSIS OF MONITORING WELL SAMPLES FROM THE MCCOOK RESERVOIR SITE
LOCATION: VARIOUS
ESTIMATE: $93,182.00
GROUP: TOTAL
A3 ENVIRONMENTAL, LLC $64,272.00
BOTRAN TECHNOLOGY, LLC $70,325.00
TECHLAW, INC. $79,834.10
TETRA TECH, INC. $93,519.89
BBJ GROUP, LLC $117,200.00
ANDREWS ENGINEERING, INC. $121,549.00
BIDDERS NOTIFIED: 344 PLANHOLDERS: 26
Respectfully Submitted, Darlene A. LoCascio, Director of Procurement and Materials Management