To watch the live meeting proceedings, please refresh this page at the scheduled meeting time, a link labeled "In Progress" will appear under the Video column
File #: 20-0211    Version: 1
Type: Agenda Item Status: Adopted
File created: 2/26/2020 In control: Procurement Committee
On agenda: 3/5/2020 Final action: 3/5/2020
Title: Issue purchase order for Contract 20-105-12 (Re-Bid), Inspection, Maintenance, and Repair of Lysimeters and Groundwater Monitoring Wells, to Patrick Engineering, Inc., in an amount not to exceed $36,000.00, Account 101-16000-612490, Requisition 1527684

TRANSMITTAL LETTER FOR BOARD MEETING OF MARCH 5, 2020

 

COMMITTEE ON PROCUREMENT

 

Mr. Brian A. Perkovich, Executive Director

 

Title

Issue purchase order for Contract 20-105-12 (Re-Bid), Inspection, Maintenance, and Repair of Lysimeters and Groundwater Monitoring Wells, to Patrick Engineering, Inc., in an amount not to exceed $36,000.00, Account 101-16000-612490, Requisition 1527684

Body

 

Dear Sir:

 

On September 19, 2019, the Board of Commissioners authorized the Director of Procurement and Materials Management to advertise for bids, Contract 20-105-11, Inspection, Maintenance, and Repair of Lysimeters and Groundwater Monitoring Wells.  The contract will expire on December 31, 2021.

 

In response to a public advertisement of October 23, 2019, a bid opening was held on November 12, 2019.  No bids were received for this contract. 

 

In response to a public re-advertisement of January 8, 2020, a bid opening was held on January 28, 2020.  The bid tabulation for this contract is:

 

                     PATRICK ENGINEERING, INC.                     $36,000.00

 

One thousand one hundred thirty-six (1,136) companies were notified of this contract being advertised and nineteen (19) companies requested specifications.

 

The Director of Procurement and Materials Management has reviewed the bidders’ list for this contract and is satisfied that the market for this service has been adequately solicited.  A planholders’ survey revealed the following reasons for not bidding:  outside their scope of work.  In light of these findings, the Director of Procurement and Materials Management is of the opinion that the bid received is a fair and reasonable price, and nothing would be gained by rejecting the sole bid and re-advertising this contract.

 

Patrick Engineering, Inc., the sole bidder, is proposing to perform the contract in accordance with the specifications.  The estimated cost for this contract was $30,000.00, placing their bid of $36,000.00 approximately 20 percent above the estimate.

 

The Multi-Project Labor Agreement was not included in this contract because the classification of work does not fall within the provisions of the MPLA.

 

The Affirmative Action Ordinance, Revised Appendix D and Appendix V were not included in this contract because the estimate is less than the minimum threshold established by Section 4 of the Affirmative Action Ordinance.

 

In view of the foregoing, it is recommended that the Director of Procurement and Materials Management be authorized to issue a purchase order for Contract 20-105-12 (Re-Bid) to Patrick Engineering, Inc., in an amount not to exceed $36,000.00.

 

No bid deposit was required for this contract.

 

Funds for the 2020 expenditure, in the amount of $18,000.00, are available in Account 101-16000-612490.  The estimated expenditure for 2021 is $18,000.00.  Funds for the 2021 expenditure is contingent on the Board of Commissioners’ approval of the District’s budget for that year.

  

Recommended, Darlene A. LoCascio, Director of Procurement and Materials Management, DAL:SEB:cm

Respectfully Submitted, Barbara J. McGowan, Chairman Committee on Procurement

Disposition of this agenda item will be documented in the official Regular Board Meeting Minutes of the Board of Commissioners for March 5, 2020