TRANSMITTAL LETTER FOR BOARD MEETING OF MARCH 5, 2020

 

COMMITTEE ON PROCUREMENT

 

Mr. Brian A. Perkovich, Executive Director

 

Title

Report of bid opening of Tuesday, February 11, 2020

Body

 

Dear Sir:

 

Bids were received and opened on 2/11/2020 for the following contracts:

 

CONTRACT 13-248-5F STREAMBANK STABILIZATION ON MELVINA DITCH

LOCATION:  MELVINA DITCH RESERVOIR

ESTIMATE:  $10,877,685.25

GROUP: TOTAL 

                     RAUSCH INFRASTRUCTURE, LLC                     $9,847,000.00

                     INDUSTRIA, INC.                     $9,947,947.00

                     DUNTEMAN COMPANY, R .W.                       $10,835,000.00

                     PATH CONSTRUCTION COMPANY, INC.                     $10,883,871.90

                     PAN-OCEANIC ENGINEERING CO., INC.                     $10,981,000.00

                     IHC CONSTRUCTION COMPANIES, LLC                     $12,140,000.00

 

                     BIDDERS NOTIFIED:  1112                     PLANHOLDERS:  67

 

CONTRACT 18-803-32 GRAVITY CONCENTRATION TANK REHABILITATION AT THE CALUMET WATER RECLAMATION PLANT (RE-BID)

LOCATION:  CALUMET

ESTIMATE:  $2,300,000.00

GROUP: TOTAL 

                     INDEPENDENT MECHANICAL INDUSTRIES, INC.                     $2,295,800.00

                     IHC CONSTRUCTION COMPANIES, LLC                     $2,360,000.00

                     JOSEPH J. HENDERSON & SON, INC.                     $2,458,000.00

                     BROADWAY ELECTRIC, INC.                     $2,663,000.00

 

                     BIDDERS NOTIFIED:  1181                     PLANHOLDERS:  61

 

CONTRACT 20-611-11 REPAIRS AND ALTERATIONS TO VARIOUS WATER RECLAMATION FACILITIES

LOCATION:  VARIOUS

ESTIMATE:  $13,430,500.00

GROUP: TOTAL 

                     INDEPENDENT MECHANICAL INDUSTRIES, INC.                     $13,623,128.00

                     ANCHOR MECHANICAL, INC.                     $20,487,858.00

 

                     BIDDERS NOTIFIED:  956                     PLANHOLDERS:  55

 

CONTRACT 20-632-11 FURNISHING AND DELIVERING SODIUM HYPOCHLORITE

LOCATION:  VARIOUS

ESTIMATE:  $4,206,963.00

GROUP: TOTAL 

                    

                     ALEXANDER CHEMICAL CORPORATION                     $3,322,535.73

                     ROWELL CHEMICAL CORPORATION                     $3,553,744.44

                     OLIN CORPORATION                      $4,401,809.30

 

                     BIDDERS NOTIFIED:  353                     PLANHOLDERS:  16

 

CONTRACT 20-655-11 MANHOLE AND INFRASTRUCTURE REPAIRS

LOCATION:  VARIOUS

ESTIMATE:  $600,000.00

GROUP: TOTAL 

                     ED WEATHERSBY & SONS PLUMBING, WATER &                     $544,163.00

                     SEWERS, INC.

                     SUMIT CONSTRUCTION CO., INC.                     $555,655.00

                     MISFITS CONSTRUCTION COMPANY                     $583,075.00

                     NORTHWEST GENERAL CONTRACTORS, INC.                     $587,265.00

                     PAN-OCEANIC ENGINEERING COMPANY, INC.                     $594,635.00

 

                     BIDDERS NOTIFIED:  582                     PLANHOLDERS:  38

 

Respectfully Submitted, Darlene A. LoCascio, Director of Procurement and Materials Management