TRANSMITTAL LETTER FOR BOARD MEETING OF JUNE 4, 2020
COMMITTEE ON FINANCE
Mr. Brian A. Perkovich, Executive Director
Title
Authority to add Project 20-704-21, Rehabilitate One Electric Motor at the O’Brien Water Reclamation Plant, to the Construction Fund, estimated cost of the project is $250,000.00
Body
Dear Sir:
Authority is requested to add Project 20-704-21, Rehabilitate One Electric Motor at the O’Brien Water Reclamation Plant, to the Construction Fund, at the request of the Maintenance and Operations Department.
The project consists of the off-site rehabilitation of one 1,000 horsepower, horizontal shaft, synchronous pump motor. District trades will perform all on-site labor.
The estimated cost of this project is $250,000.00.
Requested, John P. Murray, Director of Maintenance and Operations, EJS:BK:MAG:JR:NRE
Respectfully Submitted, Frank Avila, Chairman Committee on Finance
Disposition of this agenda item will be documented in the official Regular Board Meeting Minutes of the Board of Commissioners for June 4, 2000