TRANSMITTAL LETTER FOR BOARD MEETING OF AUGUST 8, 2013
COMMITTEE ON PROCUREMENT
Mr. David St. Pierre, Executive Director
Title
Report of bid opening of Tuesday, July 9, 2013
Body
Dear Sir:
Bids were received and opened on 7/9/2013 for the following contracts:
CONTRACT 11-241-3P DISINFECTION FACILITIES CALUMET WATER RECLAMATION PLANT
LOCATION: CALUMET
ESTIMATE: $33,000,000.00
GROUP: TOTAL
F.H. PASCHEN, SN NIELSEN & ASSOCIATES LLC $30,360,000.00
IHC/KED, A JOINT VENTURE $30,820,000.00
SOLLITT,/SACHI/ALWORTH JOINT VENTURE $34,090,000.00
ONEIL, W. E. CONSTRUCTION COMPANY $34,253,000.00
WALSH CONSTRUCTION COMPANY $35,893,618.00
KENNY CONSTRUCTION COMPANY $38,204,100.00
BIDDERS NOTIFIED: 746 PLANHOLDERS: 110
CONTRACT 11-961-21 FACILITY ROOF REPLACEMENTS AND ASSOCIATED TUCKPOINTING AT THE STICKNEY WATER RECLAMATION PLANT AND THE LAWNDALE AVENUE SOLIDS MANAGEMENT AREA
LOCATION: STICKNEY
ESTIMATE: $2,790,600.00
GROUP: TOTAL
L. MARSHALL, INC. $2,891,000.00
PATH CONSTRUCTION COMPANY, INC. $3,059,000.00
BULLEY & ANDREWS MASONRY RESTORATION $3,262,000.00
LLC
TYLER LANE CONSTRUCTION, INC. $3,677,531.00
BIDDERS NOTIFIED: 598 PLANHOLDERS: 35
CONTRACT 13-430-21 FURNISH AND DELIVER ONE NEW REFRIGERATION VAN AND TWO NEW VANS WITH CAMPLER STYLE HIGH-TOPS
LOCATION: STICKNEY
ESTIMATE: $90,000.00
GROUP: A REFRIGERATION VAN
BCR AUTOMOTIVE GROUP $47,650.00
GROUP: B TWO VANS WITH CAMPER STYLE HIGH-TOP
BCR AUTOMOTIVE GROUP $81,600.00
BIDDERS NOTIFIED: 138 PLANHOLDERS: 9
Respectfully Submitted, Darlene A. LoCascio, Director of Procurement and Materials Management