File #: 13-0838    Version: 1
Type: Agenda Item Status: Adopted
File created: 7/30/2013 In control: Procurement Committee
On agenda: 8/8/2013 Final action: 8/8/2013
Title: Authority to award Contract 13-025-11, Furnish and Deliver Plumbing Pipe, Fittings and Valves to Various Locations for a One (1) Year Period, Groups A, B & C, to Johnson Pipe & Supply Company, Inc., in a total amount not to exceed $228,592.20, Account 101-20000-623090
Attachments: 1. Contract 13-025-11- Group A Item Descriptions.pdf, 2. Contract 13-025-11 - Group B Item Descriptions.pdf, 3. Contract 13-025-11 - Group C Item Descriptions.pdf
TRANSMITTAL LETTER FOR BOARD MEETING OF AUGUST 8, 2013
 
COMMITTEE ON PROCUREMENT
 
Mr. David St. Pierre, Executive Director
 
Title
Authority to award Contract 13-025-11, Furnish and Deliver Plumbing Pipe, Fittings and Valves to Various Locations for a One (1) Year Period, Groups A, B & C, to Johnson Pipe & Supply Company, Inc., in a total amount not to exceed $228,592.20, Account 101-20000-623090
Body
 
Dear Sir:
 
On April 18, 2013, the Board of Commissioners authorized the Director of Procurement and Materials Management to advertise for bids, Contract 13-025-11 furnish and deliver plumbing pipe, fittings and valves to various locations for a one year period, beginning approximately September 1, 2013 and ending August 31, 2014.
 
In response to a public advertisement of May 8, 2013, a bid opening was held on June 11, 2013.  The bid tabulation for this contract is:
 
GROUP A: PIPE
JOHNSON PIPE & SUPPLY COMPANY, INC.      *$35,417.74
GRIFFITH WINDUSTRIAL COMPANY      $39,377.52
COLUMBIA PIPE & SUPPLY COMPANY      $45,808.82
 
GROUP B: PIPE FITTINGS
JOHNSON PIPE & SUPPLY COMPANY, INC.      *$86,817.66
GRIFFITH WINDUSTRIAL COMPANY      *$90,828.62
COLUMBIA PIPE & SUPPLY COMPANY      *105,928.65
 
GROUP C: VALVES
JOHNSON PIPE & SUPPLY COMPANY, INC.      $106,356.80
GRIFFITH WINDUSTRIAL COMPANY      *$123,561.63
COLUMBIA PIPE & SUPPLY COMPANY      *$124,264.89
      *corrected total
 
Six hundred ninety-four (694) companies were notified of the contract being advertised and thirty-five (35) companies requested specifications.
 
Johnson Pipe & Supply Company, Inc., the lowest responsible bidder for Groups A, B and C is proposing to perform the contract in accordance with the specifications. The estimated cost for Groups A, B and C of this contract was $258,000.00, placing the total bid of $228,592.20 approximately 11.4 percent below the estimate.
 
The Multi-Project Labor Agreement (MPLA) is not applicable to this contract because it is primarily a furnish and deliver contract.
 
The Affirmative Action Interim Ordinance Appendix D is not included in this contract because it is primarily a furnish and deliver contract.
 
In view of the foregoing, it is recommended that the Director of Procurement and Materials Management be authorized to award Contract 13-025-11, to Johnson Pipe & Supply Company, Inc., in a total amount not to exceed $228,592.20
 
Purchase orders will be issued for the material as required.  Payment will be based on the unit cost as indicated in the contract documents.  Funds are available in Account 101-20000-623090.
 
Recommended, Darlene A. LoCascio, Director of Procurement and Materials Management, DAL:SEB:MB:np
Respectfully Submitted, Barbara J. McGowan, Chairman Committee on Procurement
Disposition of this agenda item will be documented in the official Regular Board Meeting Minutes of the Board of Commissioners for August 8, 2013
 