TRANSMITTAL LETTER FOR BOARD MEETING OF JANUARY 21, 2010
COMMITTEE ON PROCUREMENT
Mr. Richard Lanyon, Executive Director
Title
Report of bid opening of Tuesday, January 5, 2010
Body
Dear Sir:
Bids were received and opened on 1/5/2010 for the following contracts:
CONTRACT 09-685-11 FURNISHING AND DELIVERING RAIN BARRELS TO VARIOUS LOCATIONS
LOCATION: VARIOUS
ESTIMATE: $296,000.00
GROUP: TOTAL
UPCYCLE PRODUCTS, INC. $235,000.00
MEESE ORBITRON DUNNE CO $262,350.00
STEINER ELECTRIC COMPANY $269,750.00
ROOT BROTHERS MANUFACTURING & SUPPLY $349,750.00
COMPANY
BIDDERS NOTIFIED: 256 PLANHOLDERS: 11
CONTRACT 10-866-11 SECURITY SERVICES AT FULTON COUNTY, ILLINOIS
LOCATION: FULTON COUNTY
ESTIMATE: $130,000.00
GROUP: TOTAL
NO BIDS RECEIVED $0.00
BIDDERS NOTIFIED: 93 PLANHOLDERS: 12
Respectfully Submitted, Darlene A. LoCascio, Director of Procurement and Materials Management