TRANSMITTAL LETTER FOR BOARD MEETING OF FEBRUARY 18, 2010
COMMITTEE ON ENGINEERING
Mr. Richard Lanyon, Executive Director
Title
Report on change orders authorized and approved by the Director of Engineering during the month of January 2010
Body
Dear Sir:
Six change orders were approved by the Director of Engineering that cumulatively, but not individually, increased or decreased the cost of contracts by $10,000.00 or more during January 2010. The contracts and related data are listed in the attached sheet.
Please advise the undersigned if additional information is required.
Respectfully Submitted, Joseph P. Sobanski, Director of Engineering, SAF
Attachment