File #: 10-0278    Version: 1
Type: Report Status: Filed
File created: 2/24/2010 In control: Procurement Committee
On agenda: 3/4/2010 Final action: 3/4/2010
Title: Report of bid opening of Tuesday, February 23, 2010

TRANSMITTAL LETTER FOR BOARD MEETING OF MARCH 4, 2010

 

COMMITTEE ON PROCUREMENT

 

Mr. Richard Lanyon, Executive Director

 

Title

Report of bid opening of Tuesday, February 23, 2010

Body

 

Dear Sir:

 

Bids were received and opened on 2/23/2010 for the following contracts:

 

CONTRACT 10-105-12 HELICOPTER SERVICE FOR A TWO-YEAR PERIOD (RE-BID)

LOCATION:  VARIOUS

ESTIMATE:  $41,400.00

GROUP: TOTAL 

                     LEN JABLON HELICOPTERS, INC.                     $35,820.00

                     HELIMOTION LLC                     $63,000.00

 

                     BIDDERS NOTIFIED:  34                     PLANHOLDERS:  4

 

CONTRACT 10-611-11 REPAIRS AND ALTERATIONS TO VARIOUS WATER RECLAMATION FACILITIES IN THE STICKNEY SERVICE AREA AND OTHER INSTALLATIONS

LOCATION:  STICKNEY

ESTIMATE:  $5,720,000.00

GROUP: TOTAL 

                     ANCHOR MECHANICAL, INC.                     $5,772,177.40

                     INDEPENDENT MECHANICAL INDUSTRIES, INC.                     $5,839,434.00

                     PATH CONSTRUCTION COMPANY, INC.                     $6,378,354.60

                     ENERFAB, INC.                     $6,629,795.34

                     HAYES MECHANICAL LLC                     $7,706,739.00

 

                     BIDDERS NOTIFIED:  524                     PLANHOLDERS:  35

 

CONTRACT 10-677-11 OVERHEAD AND EXTERIOR DOOR MAINTENANCE SERVICES AT VARIOUS SERVICE AREAS

LOCATION:  VARIOUS

ESTIMATE:  $346,000.00

GROUP: TOTAL 

                     ANAGNOS DOOR COMPANY, INC.                     $424,618.00

                     KONEMATIC, INC. D/B/A DOOR SYSTEMS, INC.                     $456,970.00

                     BUILDERS CHICAGO CORPORATION                     $555,650.00

 

                     BIDDERS NOTIFIED:  141                     PLANHOLDERS:  12

 

Respectfully Submitted, Darlene A. LoCascio, Director of Procurement and Materials Management