To watch the live meeting proceedings, please refresh this page at the scheduled meeting time, a link labeled "In Progress" will appear under the Video column
File #: 10-0598    Version: 1
Type: Agenda Item Status: Adopted
File created: 4/29/2010 In control: Procurement Committee
On agenda: 5/6/2010 Final action: 5/6/2010
Title: Authority to decrease Contract 09-616-11, Switchgear Maintenance and Repair at Various Service Areas, to American Industrial Motor Service, in an amount of $50,413.81, from an amount of $476,583.00, to an amount not to exceed $426,169.19, Accounts 101-67000, 68000-612600, Purchase Orders 5001077, 5001080
Attachments: 1. 09-616-11(4).pdf

TRANSMITTAL LETTER FOR BOARD MEETING OF MAY 6, 2010

 

COMMITTEE ON PROCUREMENT

 

Mr. Richard Lanyon, Executive Director

 

Title

Authority to decrease Contract 09-616-11, Switchgear Maintenance and Repair at Various Service Areas, to American Industrial Motor Service, in an amount of $50,413.81, from an amount of $476,583.00, to an amount not to exceed $426,169.19, Accounts 101-67000, 68000-612600, Purchase Orders 5001077, 5001080

Body

 

Dear Sir:

 

On September 3, 2009, the Board of Commissioners authorized the Director of Procurement and Materials Management to award Contract 09-616-11, Switchgear Maintenance and Repair at Various Service Areas, to American Industrial Motor Service, in an amount not to exceed $491,000.00. The contract expired on March 27, 2010.

 

As of April 9, 2010, the attached list of change orders has been approved. The effect of these change orders resulted in a decrease in an amount of $14,417.00 to the original amount awarded of $491,000.00. The current contract value is $476,583.00. The prior approved change orders reflect a 2.9% decrease to the original contract value.

 

Due to less than anticipated use of the services in 2010, funds will not be utilized.

 

This change order is in compliance with the Illinois Criminal Code since the change is due to circumstances not reasonably foreseeable at the time the contract was signed, and is in the best interest of the District.

 

It is hereby recommended that the Board of Commissioners authorize the Director of Procurement and Materials Management to execute a change order to decrease Contract 09-616-11 in an amount of $50,413.81 (approximately 10.6% of the current contract value), from an amount of $476,583.00, to an amount not to exceed $426,169.19.

 

Funds will be restored in Accounts 101-67000, 68000-612600.

 

Requested, Osoth Jamjun, Director of Maintenance and Operations, OJ:MPS:SO’C:MAG:LSC:IJA

Recommended, Darlene A. LoCascio, Director of Procurement and Materials Management

Respectfully Submitted, Barbara J. McGowan, Chairman Committee on Procurement

Disposition of this agenda item will be documented in the official Regular Board Meeting Minutes of the Board of Commissioners for May 6, 2010

 

Attachment