File #: 10-0722    Version: 1
Type: Agenda Item Status: Adopted
File created: 6/9/2010 In control: Procurement Committee
On agenda: 6/17/2010 Final action: 6/17/2010
Title: Authority to advertise Contract 10-616-11 Switchgear Maintenance and Repair at Various Service Areas, estimated cost $255,000.00, Accounts 101-69000-612650, 101-69000/68000/67000-612600, Requisitions 1295019, 1299681, 1302107

TRANSMITTAL LETTER FOR BOARD MEETING OF JUNE 17, 2010

 

COMMITTEE ON PROCUREMENT

 

Mr. Richard Lanyon, Executive Director

 

Title

Authority to advertise Contract 10-616-11 Switchgear Maintenance and Repair at Various Service Areas, estimated cost $255,000.00, Accounts 101-69000-612650, 101-69000/68000/67000-612600, Requisitions 1295019, 1299681, 1302107

Body

 

Dear Sir:

 

Contract documents and specifications have been prepared for the procurement of services to perform preventive maintenance and repairs on medium voltage switchgear and their associated protective equipment and components, in the Stickney, Calumet and Kirie Service Areas. The services will ensure the safe, efficient and reliable operation of the switchgear and other equipment and accessories at these locations.

 

The estimated cost for this contract is $255,000.00.

 

The bid deposit for this contract is $12,750.00.

 

The contract specifications require all work to begin on or about September 1, 2010, and terminate by December 31, 2010. Liquidated damages are one hundred dollars ($100.00) for each day the contractor is in default of performing the specified work, as required and ordered by the Engineer, and twenty five dollars ($25.00) for each day that he is in default of the time specified for submitting all required documentation for the work.

 

The Multi-Project Labor Agreement and the Revised Appendix D are not included in this contract because the work involves the servicing, testing and calibration of switchgear and protective relaying. This work can only be performed by the equipment manufacturer’s engineers, or by other highly skilled technicians trained in the servicing of similar equipment and certified by a national accrediting body. If any trade work is required, it will be performed by in-house labor forces.

 

The tentative schedule for this contract is as follows:

Advertise                     June 23, 2010

Bid Opening                     July 13, 2010

Award                     August 12, 2010

Completion                     December 31, 2010

 

Funds are available in Accounts 101-69000-612650, 101-69000/68000/67000-612600.

 

In view of the foregoing, it is recommended that the Director of Procurement and Materials Management be authorized to advertise Contract 10-616-11.

 

Requested, Manju Prakash Sharma, Acting Director of Maintenance and Operations, MPS:SO’C:MAG:LSC:IJA

Recommended, Darlene A. LoCascio, Director of Procurement and Materials Management

Respectfully Submitted, Barbara J. McGowan, Chairman Committee on Procurement