Title: Authority to settle the Workers’ Compensation Claim of Bernard Ellis vs. MWRDGC, Claim No. 0200005424, Illinois Workers’ Compensation Commission (IWCC), in the sum of $13,219.82. Account 901-30000-601090
TRANSMITTAL LETTER FOR BOARD MEETING OF MAY 2, 2013
 
COMMITTEE ON JUDICIARY
 
Mr. David St. Pierre, Executive Director
 
Title
Authority to settle the Workers' Compensation Claim of Bernard Ellis vs. MWRDGC, Claim No. 0200005424, Illinois Workers' Compensation Commission (IWCC), in the sum of $13,219.82.  Account 901-30000-601090
Body
 
Dear Sir:
 
Bernard Ellis is a Maintenance Laborer A (Shift) who works at the Stickney Water Reclamation Plant.  On April 23, 2012, he injured his left shoulder at work.  An MRI of the left shoulder indicated that he sustained a mild non-displaced fracture of the humeral head.  After undergoing conservative treatment, Mr. Ellis was able to return to work on June 7, 2012.  He was paid a total of six weeks of lost time benefits for this injury.
 
Subject to approval of the IWCC, this pro se claim can now be settled for the sum of $13,219.82, which represents 3.8% loss of use of the body as a whole.  This settlement will close out any future lost time benefits as well as any future medical exposure on this claim.
The General Counsel believes this settlement is in the best interest of the District and requests payment of that sum be approved and he be authorized to execute such documents as may be necessary to effect the settlement.
 
Requested, Ronald M. Hill, General Counsel, RMH:LAG:RG:nm
Respectfully Submitted, Mariyana T. Spyropoulos, Chairman Committee on Judiciary
Disposition of this agenda item will be documented in the official Regular Board Meeting Minutes of the Board of Commissioners for May 2, 2013