13
Authority to award Contract 23-379-3E, Electrical Power Distribution and
Phosphorus Removal Improvements, Kirie Water Reclamation Plant (KWRP),
to Sollitt/Broadway Joint Venture, in an amount not to exceed $25,766,427.00,
plus a five (5) percent allowance for change orders in an amount of
$1,288,321.35, for a total amount not to exceed $27,054,748.35, Accounts
401-50000-645650/645750, Requisition 1642737
Attachments:
Increase Purchase Order/Change Order
14
Authority to decrease Contract 21-863-2C Master Plan for Salt Creek at
Fullersburg Woods, to V3 Construction Group, LTD in a net credit amount of
$162,951.12, from an amount of $9,476,846.72, to an amount not to exceed
$9,313,895.60, Account 201-50000-612400, Purchase Order No. 4000104
Attachments:
Budget & Employment Committee
Authorization
15
Authorization to execute change orders to decrease purchase orders or
carryforward FY2025 encumbrances to FY2026 (As Revised)
Attachments:
Engineering Committee
Report
16
Report on change orders authorized and time extensions from October through
December 2025 for Contract 11-187-3F Addison Creek Channel Improvements,
SSA
Attachments:
Real Estate Development Committee
Authorization
17
Authority to issue a one (1) day permit to Friends of the Chicago River to
access District real estate at 25 locations along the North Branch of the
Chicago River, North Shore Channel, Main Channel, and Cal-Sag Channel in
Cook County, Illinois for its annual Chicago River Day cleanup event on May 9,
2026. Consideration shall be a nominal fee of $10.00
Attachments: