7
8
Report of bid opening of Tuesday, January 23, 2024
Authorization
Authorization for payment to the Water Research Foundation for the 2024
Annual Research Commitment in an amount not to exceed $172,937.00,
Account 101-15000-612280
Attachments:
9
Authorization for payment to JULIE, Inc., for participation in underground
project coordination, in an amount not to exceed $50,411.64, Account
101-50000-612430
Authority to Advertise
10
Authority to advertise Contract 23-RFP-23 Deferred Compensation Plan
Administrator, for a five-year period effective January 1, 2025 to December 31,
2029 (Deferred from the January 4, 2024 Board Meeting)(Deferred from the
January 18, 2024 Board Meeting)
Attachments:
Legislative History
1/4/24
Board of Commissioners
Board of Commissioners
Deferred
Deferred
1/18/24
11
12
13
Authority to advertise Contract 24-709-11, Furnishing and Delivering Calcium
Nitrate to the Kirie Water Reclamation Plant, estimated cost $270,000.00,
Account 101-66000-623560, Requisition 1607451
Attachments:
Authority to advertise Contract 24-641-11, Furnishing and Delivering Liquid
Carbon Dioxide to the Stickney Water Reclamation Plant, estimated cost
$2,153,500.00, Account 101-69000-623560, Requisition 1611808
Attachments:
Authority to advertise Contract 24-RFP-02 Commercial Banking and
Investment Custody Services for a five-year period, estimated cost
$413,000.00, Account 101-11000-612430, Requisitions 1611818, 1611819,
and 1611820
Attachments:
Issue Purchase Order
14
Issue purchase order to Emerson Process Management Power & Water
Solutions, Inc., to Furnish and Deliver Various Parts, Controllers, Software
Licenses, and Upgrades to the Ethernet IO and DCS System at the Stickney
Water Reclamation Plant, Waterways Section, and the North Service Area, in
an amount not to exceed $381,725.00, Account 101-69000-623070,
Requisitions 1611151, 1611152 and 1611154