TRANSMITTAL LETTER FOR BOARD MEETING OF NOVEMBER 19, 2026

 

COMMITTEE ON JUDICIARY

 

Mr. John P. Murray, Executive Director

 

Title

Authority to settle the Workers’ Compensation Claim of Donald McGrew vs. MWRDGC, Claim number 23WC020872 Illinois Workers’ Compensation Commission (IWCC), in the sum of $61,300.00, Account 901-30000-601090

Body                    

 

Dear Sir:

 

Donald McGrew is an Operating Engineer II at the O’Brien Water Reclamation Plant. On June 24, 2023, he reported that while inspecting RASP-C, he stepped down from the pump foundation onto an oil spot at the base level of the pump. He slipped and twisted his right knee.

 

Mr. McGrew sought treatment at the Industrial Clinic on June 24, 2023, and was diagnosed with a strain. He treated conservatively with physical therapy.

 

On July 18, 2023, Mr. McGrew was taken off work. An MRI revealed meniscal tears, including a full thickness radial tear at the medial meniscal posterior horn. An MCL sprain, significant wearing of the cartilage, and a ruptured Bakers Cyst were also noted.

 

Mr. McGrew was released to return to work, with restrictions, on September 15, 2023.

 

On November 27, 2023, Mr. McGrew underwent a right knee arthroscopic partial medial meniscectomy, chondroplasty, and extensive synovectomy. He was off work as of November 27, 2023, and returned to work on December 19, 2023.

 

Mr. McGrew was paid a total of 12.6 weeks of lost time benefits totaling $19,306.13.

 

Mr. McGrew filed an Application of Adjustment of Claim with the Illinois Workers’ Compensation Commission (IWCC) through his counsel. Subject to the approval of the IWCC, this case can be settled for $61,300.00 representing approximately 28.57% loss of use of the right leg. This settlement will close out any future lost time and medical benefits.

 

The Director of Human Resources believes this settlement is in the best interest of the District and requests payment of that sum be approved and he be authorized to execute such documents as may be necessary to effect the settlement.

 

Requested, James E. Fisher, Director of Human Resources, JEF:BLW:DMG

Disposition of this agenda item will be documented in the official Regular Board Meeting Minutes of the Board of Commissioners for November 19, 2026