TRANSMITTAL LETTER FOR BOARD MEETING OF MAY 21, 2020
COMMITTEE ON FINANCE
Mr. Brian A. Perkovich, Executive Director
Title
Authority to add Project 20-703-21 Furnish and Deliver a Lathe and Accessories to the O’Brien Water Reclamation Plant, to the Construction Fund, estimated cost of the project is $170,000.00
Body
Dear Sir:
Authority is requested to add Project 20-703-21 Furnish and Deliver a Lathe and Accessories to the O’Brien Water Reclamation Plant, to the Construction Fund, at the request of the Maintenance and Operations Department.
The project consists of procuring a lathe and accessories that will be used for day-to-day machining at the O’Brien Water Reclamation Plant. The lathe will replace a 40-year-old unit that has reached the end of its useful life.
The estimated cost of the project is $170,000.00.
Requested, John P. Murray, Director of Maintenance and Operations, EJS:BK:MAG:JR
Respectfully Submitted, Frank Avila, Chairman Committee on Finance
Disposition of this agenda item will be documented in the official Regular Board Meeting Minutes of the Board of Commissioners for May 21, 2020