TRANSMITTAL LETTER FOR BOARD MEETING DECEMBER 19, 2019
COMMITTEE ON PROCUREMENT
Mr. Brian A. Perkovich, Executive Director
Title
Authorization to amend Board Order of August 8, 2019, regarding Authority to advertise Contract 18-277-3M Digester Sludge Heating System Upgrades and Boiler Removal, Calumet Water Reclamation Plant, estimated cost between $27,075,000.00 and $32,775,000.00, Account 401-50000-645750, Requisition 1524789, Agenda Item No. 35, File No. 19-0745
Body
Dear Sir:
At the board meeting of August 8, 2019, the Board of Commissioners duly authorized the above stated action, Agenda Item No. 35, File No. 19-0745.
A textual error in the title/transmittal letter and resulting order indicated, The type of work to be performed under the contract is within the “General and Heavy Construction” category. Same should have read, The type of work to be performed under the contract is within the “Mechanical” category.
All other information provided in the transmittal is correct.
Therefore, it is requested that the aforesaid Board order of August 8, 2019 be amended to effect the changes set forth above, otherwise to remain in force and effect as heretofore enacted.
Requested, Catherine A. O’Connor, Director of Engineering, ECB:LMK
Recommended, Darlene A. LoCascio, Director of Procurement and Materials Management
Respectfully Submitted, Barbara J. McGowan, Chairman Committee on Procurement
Disposition of this agenda item will be documented in the official Regular Board Meeting Minutes of the Board of Commissioners for December 19, 2019
Attachment