On agenda: 7/17/2025 Final action: 7/17/2025
Title: Authority to advertise Contract 25-617-11, Power Distribution Equipment Inspection and Repairs, in an amount not to exceed $735,000.00, Accounts 101-67000/68000/69000-612650/623070, Requisitions 1641184, 1641186 and 1641187
Attachments: 1. Contract 25-617-11 Affirmative Action Goals Report

TRANSMITTAL LETTER FOR BOARD MEETING OF JULY 17, 2025

 

COMMITTEE ON PROCUREMENT

 

Mr. John P. Murray, Acting Executive Director

 

Title

Authority to advertise Contract 25-617-11, Power Distribution Equipment Inspection and Repairs, in an amount not to exceed $735,000.00, Accounts 101-67000/68000/69000-612650/623070, Requisitions 1641184, 1641186 and 1641187

Body

 

Dear Sir:

 

Contract documents and specifications have been prepared for Contract 25-617-11, Power Distribution Equipment Inspection and Repairs, at the request of the Maintenance and Operations Department.

 

The purpose of this contract is to provide testing and repair services and replacement parts to maintain power distribution equipment for District facilities.

 

The estimated cost of this contract is not to exceed $735,000.00. The estimated 2025, 2026, 2027, and 2028 expenditures are $15,000.00 for 2025, and $240,000.00 per year for 2026, 2027, and 2028.

 

The Multi-Project Labor Agreement (MPLA) will be included in this contract.

 

The Affirmative Action Ordinance, Revised Appendix D and Appendix V will not be included in this contract due to the limited availability of MBE/WBE/VBE participants and the specialized nature of the services.

 

The tentative schedule for this contract is as follows:

Advertise                                              August 20, 2025

Bid Opening                                          September 16, 2025

Award                                                             October 2, 2025

Completion                                             December 31, 2028

 

Funds for 2025 are available in Accounts 101-67000/68000/69000-612650/623070. Funds for the following years, 2026, 2027, and 2028, are contingent on the Board of Commissioners’ approval of the District’s budget for those years.

 

In view of the foregoing, it is recommended that the Director of Procurement and Materials Management be authorized to advertise Contract 25-617-11.

 

Requested, Pinakin V. Desai, Acting Director of Maintenance and Operations, JS:MM:JR:JMC

Recommended, Darlene A. LoCascio, Director of Procurement and Materials Management

Respectfully Submitted, Precious Brady-Davis, Chairperson Committee on Procurement

Disposition of this agenda item will be documented in the official Regular Board Meeting Minutes of the Board of Commissioners for July 17, 2025

 