TRANSMITTAL LETTER FOR BOARD MEETING OF MAY 21, 2026
COMMITTEE ON PROCUREMENT
Mr. John P. Murray, Executive Director
Title
Authority to increase Contract 16-127-3DR A/B and C/D Service Tunnel Rehabilitation - Phase Three, Stickney Water Reclamation Plant, Rebid, to IHC Construction Companies, LLC in an amount of $110,166.91, from an amount of $29,408,742.77, to an amount not to exceed $29,518,909.68, Account 401-50000-645750, Purchase Order 4000097
Body
Dear Sir:
On February 2, 2023, the Board of Commissioners authorized the Director of Procurement and Materials Management to award Contract 16-127-3DR A/B and C/D Service Tunnel Rehabilitation - Phase Three, Stickney Water Reclamation Plant, Rebid, to IHC Construction Companies, LLC, in an amount not to exceed $28,872,125.00, plus a five (5) percent allowance for change orders in an amount of $1,443,606.25, for a total amount not to exceed $30,315,731.25. The scheduled contract completion date is June 14, 2026.
As of May 8, 2026, the attached list of change orders has been approved.
Original Contract Amount $28,872,125.00
Date of Board Approval 2/2/2023
Cumulative Change Order (5/8/2026) $536,617.77
% Change of Original Contract Value 1.86%
Current Contract Value $29,408,742.77
Requested Increase $110,166.91
New Contract Value $29,518,909.68
% Change of Current Contract Value 0.37%
Total % Change of Original Contract Value 2.24%
The engineer determined that certain revisions are required to repair, replace or protect deteriorated steel structures in the C/D Battery Service Tunnel that were not identified in the original contract scope. Work consists of installing one guardrail post, repairing two additional guardrail posts, and filling fifteen (15) pockets in the new floor topping with concrete to prevent water from collecting and corroding the air main supports. The contractor submitted a cost proposal (CO-36) for an extra in the amount of $110,166.91 and a credit in the amount of $0.00, for a net extra in the amount of $110,166.91. The engineer reviewed the proposal, found it to be reasonable, and stated via correspondence CO36, that the Engineering Department would recommend its approval.
This change order is in compliance with the Illinois Criminal Code since the change is germane to the contract.
It is hereby recommended that the Board of Commissioners authorize the Director of Procurement and Materials Management to execute a change order to increase Contract 16-127-3DR in an amount of $110,166.91 (0.37% of the current contract value), from an amount of $29,408,742.77, to an amount not to exceed $29,518,909.68.
Funds are available in Account 401-50000-645750.
Requested, Catherine A. O’Connor, Director of Engineering, CS:GRR
Recommended, Darlene A. LoCascio, Director of Procurement and Materials Management
Respectfully Submitted, Precious Brady-Davis, Chairperson Committee on Procurement
Disposition of this agenda item will be documented in the official Regular Board Meeting Minutes of the Board of Commissioners for May 21, 2026