Skip to main content


To watch the live meeting proceedings, please refresh this page at the scheduled meeting time, a link labeled "In Progress" will appear under the Video column
File #: 08-1502    Version: 1
Type: Agenda Item Status: Adopted
File created: 6/12/2008 In control: Procurement Committee
On agenda: 6/19/2008 Final action: 6/19/2008
Title: Authority to decrease Contract 73-161-FH Vulcan Conveyance System and Maintenance Facilities, McCook CUP Reservoir, to Graycor Industrial Contractors, Inc. in an amount of $22,778.61 from an amount of $30,241,436.58, to an amount not to exceed $30,218,657.97, Account 401-50000-645620, Purchase Order 5000562
Attachments: 1. Change Order Log 6.9.08 FH.PDF

TRANSMITTAL LETTER FOR BOARD MEETING OF June 19, 2008

 

COMMITTEE ON PURCHASING

 

Mr. Richard Lanyon, General Superintendent

 

Title

Authority to decrease Contract 73-161-FH Vulcan Conveyance System and Maintenance Facilities, McCook CUP Reservoir, to Graycor Industrial Contractors, Inc. in an amount of $22,778.61 from an amount of $30,241,436.58, to an amount not to exceed $30,218,657.97, Account 401-50000-645620, Purchase Order 5000562

Body

 

Dear Sir:

 

On May 18, 2006, the Board of Commissioners passed an order authorizing the Purchasing Agent to award Contract 73-161-FH Vulcan Conveyance System and Maintenance Facilities, McCook CUP Reservoir, to Graycor Industrial Contractors, Inc. in an amount not to exceed $29,387,000.00. The contract terms called for the completion of all work by August 29, 2007.  This contract is still in progress.

 

As of June 9, 2008, the attached list of Change Orders has been approved.  The effect of these Change Orders resulted in an increase in an amount of $854,436.58 from the original amount awarded of $29,387,000.00. The current contract value is $30,241,436.58. The prior approved Change Orders reflect a 2.9% increase to the original contract value.

 

Item 1: An extra in an amount not to exceed $22,866.80 for the installation of an additional 600 feet of aerial cable for Conveyors A and B.

 

The quantity of cable shown on sheet E-123 of the Contract Plans was 600 feet less than required.

 

The contractor submitted a cost proposal (COR-54) in the amount of $22,866.80.  After reviewing the contractor’s proposal and performing an independent estimate, the District accepted the proposal (FL-414).  The District now recommends approval for the above extra work.

 

Item 2:  A credit in an amount not to exceed $62,040.00 for certain portions of the site electrical work that could not be installed due to conflicts with the slurry wall work being performed by the Army Corps of Engineers.  Materials and equipment delivered to the site for this work will be turned over to the District and need to be installed at a later date.

 

The contractor submitted a cost proposal (COR-60) in the amount of $62,040.00.  After reviewing the contractor’s proposal and performing an independent estimate, the District accepted the proposal (FL-446).  The District now recommends approval for the above credit.

 

Item 3:  An extra in an amount not to exceed $16,394.59 for additional stone fill to facilitate access to the crusher area.

 

The contractor submitted a cost proposal (COR-26) in the amount of $28,226.16.  After reviewing the contractor’s proposal and performing and independent estimate, the District rejected the proposal (FL-427 and FL 443).  The contractor accepted the District’s counter-proposal of $16,394.59 via GICI-209.  The District now recommends approval for the above extra.

 

All three of these Change Orders are in compliance with the Illinois Criminal Code, since the Change Order is due to circumstances not reasonably foreseeable, and are in the best interest of the District.

 

It is hereby requested that the Board of Commissioners authorize the Purchasing Agent to execute three Change Orders, one for an extra in an amount not to exceed $22,866.80, one for a credit in an amount not to exceed $62,040.00, and one for an extra in an amount not to exceed $16,394.59, consisting of a decrease to Contract 73-161-FH in a total amount of $22,778.61 (.08% of the current contract value) from an amount of $30,241,436.58 to an amount not to exceed $30,218,657.97.

 

Funds will be restored in Account 401-50000-645620.

 

Requested, Joseph Sobanski, Chief Engineer, JPS:NV:MVL

Recommended, Darlene A. LoCascio, Purchasing Agent     

Respectfully Submitted, Barbara J. McGowan, Chairman Committee on Purchasing

ORDERED passed by affirmative roll call vote of a majority of the Commissioners present this June 19, 2008.  Approved, President Terrence J. O’Brien

 

Attachment